WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

TOV "KHMELNYTSKENERHOZBUT" [42035266]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 2,950,000 UAH signed 2022-12-21…2022-12-21, and the procurement plan was created later — 2022-12-23 (to 2 days after the contract); plan UA-P-2022-12-23-003762-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOV "KHMELNYTSKENERHOZBUT" [42035266]
EDRPOU code
42035266
Buyer
KP "Komunservis" [37127831]
Indicator
Procurement plan published late
Amount
UAH 2,950,000
Records behind the indicator
1
Found
5 October 2026
Code
UA-2326586
Reference
2022-12-21
Reference
2022-12-23
Reference
UA-P-2022-12-23-003762-a

What stands behind it1

  1. Contract

    Date 21 December 2022 · Amount UAH 2,950,000 · Buyer KP "Komunservis [37127831] · Supplier TOV "KHMELNYTSKENERHOZBUT [42035266] · Ref UA-2022-12-23-015889-a-b1 · procedure: reporting

Other records of this company15

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 044 October 2026Findings · Duplicate records in the data
  5. 054 October 2026Findings · Procurement under monitoring of the State Audit Service
  6. 064 October 2026Findings · Procurement under monitoring of the State Audit Service
  7. 074 October 2026Findings · Procurement under monitoring of the State Audit Service
  8. 084 October 2026Findings · Procurement under monitoring of the State Audit Service
  9. 094 October 2026Findings · Procurement under monitoring of the State Audit Service
  10. 104 October 2026Findings · Procurement under monitoring of the State Audit Service
All 15
  1. 114 October 2026Findings · Large contract without a procedure
  2. 124 October 2026Findings · Contract splitting under the threshold
  3. 134 October 2026Findings · Contract splitting under the threshold
  4. 144 October 2026Findings · Contract value inflated by amendments
  5. 154 October 2026Findings · Contract value inflated by amendments

JSONFindings · Procurement plan published late