WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

TOV "KYIVSKI ENERHETYCHNI POSLUHY" [41916045]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 99,933,134 UAH signed 2024-12-25…2024-12-25, and the procurement plan was created later — 2024-12-26 (to 1 days after the contract); plan UA-P-2024-12-26-016995-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOV "KYIVSKI ENERHETYCHNI POSLUHY" [41916045]
EDRPOU code
41916045
Buyer
KOMUNALNE PIDPRYIEMSTVO "KERUIUCHA KOMPANIIA Z OBSLUHOVUVANNIA ZHYTLOVOHO FONDU SOLOM'IANSKOHO RAIONU M. KYIEVA" [35756919]
Indicator
Procurement plan published late
Amount
UAH 99,933,134
Records behind the indicator
1
Found
5 October 2026
Code
UA-2324329
Reference
2024-12-25
Reference
2024-12-26
Reference
UA-P-2024-12-26-016995-a

What stands behind it1

  1. Contract

    Date 26 December 2024 · Amount UAH 99,933,134 · Buyer KOMUNALNE PIDPRYIEMSTVO "KERUIUCHA KOMPANIIA Z OBSLUHOVUVANNIA ZHYTLOVOHO FONDU SOLOM'IANSKOHO RAIONU M. KYIEVA [35756919] · Ref UA-2024-12-26-014873-a-b1 · procedure: reporting

Other records of this company52

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 075 October 2026Findings · Procurement plan published late
  8. 085 October 2026Findings · Procurement plan published late
  9. 095 October 2026Findings · Procurement plan published late
  10. 105 October 2026Findings · Procurement plan published late
All 52
  1. 115 October 2026Findings · Procurement plan published late
  2. 125 October 2026Findings · Procurement plan published late
  3. 135 October 2026Findings · Procurement plan published late
  4. 145 October 2026Findings · Procurement plan published late
  5. 154 October 2026Findings · Duplicate records in the data
  6. 164 October 2026Findings · Duplicate records in the data
  7. 174 October 2026Findings · Duplicate records in the data
  8. 184 October 2026Findings · Duplicate records in the data
  9. 194 October 2026Findings · Contract splitting on one day
  10. 204 October 2026Findings · Contract splitting on one day
  11. 214 October 2026Findings · Contract splitting on one day
  12. 224 October 2026Findings · Contract splitting on one day
  13. 234 October 2026Findings · Contract splitting on one day
  14. 244 October 2026Findings · Contract splitting on one day
  15. 254 October 2026Findings · Procurement under monitoring of the State Audit Service
  16. 264 October 2026Findings · Large contract without a procedure
  17. 274 October 2026Findings · Large contract without a procedure
  18. 284 October 2026Findings · Large contract without a procedure
  19. 294 October 2026Findings · Large contract without a procedure
  20. 304 October 2026Findings · Large contract without a procedure
  21. 314 October 2026Findings · Large contract without a procedure
  22. 324 October 2026Findings · Large contract without a procedure
  23. 334 October 2026Findings · Large contract without a procedure
  24. 344 October 2026Findings · Large contract without a procedure
  25. 354 October 2026Findings · Large contract without a procedure
  26. 364 October 2026Findings · Large contract without a procedure
  27. 374 October 2026Findings · Large contract without a procedure
  28. 384 October 2026Findings · Large contract without a procedure
  29. 394 October 2026Findings · Large contract without a procedure
  30. 404 October 2026Findings · Large contract without a procedure
  31. 414 October 2026Findings · Large contract without a procedure
  32. 424 October 2026Findings · Large contract without a procedure
  33. 434 October 2026Findings · Large contract without a procedure
  34. 444 October 2026Findings · Large contract without a procedure
  35. 454 October 2026Findings · Large contract without a procedure
  36. 464 October 2026Findings · Large contract without a procedure
  37. 474 October 2026Findings · Large contract without a procedure
  38. 484 October 2026Findings · Large contract without a procedure
  39. 494 October 2026Findings · Large contract without a procedure
  40. 504 October 2026Findings · Large contract without a procedure
  41. 514 October 2026Findings · Large contract without a procedure
  42. 524 October 2026Findings · Contract value inflated by amendments

JSONFindings · Procurement plan published late