WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

PrAT "Lvivoblenerho" [00131587]

Why it is here

Indicator “Procurement plan published late”: 4 contracts for 1,454,212 UAH signed 2022-02-22…2023-07-31, and the procurement plan was created later — 2022-02-24 (to 5 days after the contract); plan UA-P-2022-02-24-000927-c,UA-P-2022-12-28-001527-b,UA-P-2023-07-05-004411-c,UA-P-.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
PrAT "Lvivoblenerho" [00131587]
EDRPOU code
00131587
Buyer
Lvivskyi derzhavnyi universytet vnutrishnikh sprav [08571995]
Indicator
Procurement plan published late
Amount
UAH 1,454,212
Records behind the indicator
4
Found
5 October 2026
Code
UA-2318803
Reference
2022-02-22
Reference
2023-07-31
Reference
2022-02-24
Reference
UA-P-2022-02-24-000927-c
Reference
UA-P-2022-12-28-001527-b
Reference
UA-P-2023-07-05-004411-c

What stands behind it4

  1. Contract

    Date 31 July 2023 · Amount UAH 2,465 · Buyer Lvivskyi derzhavnyi universytet vnutrishnikh sprav [08571995] · Supplier PrAT "Lvivoblenerho [00131587] · Ref UA-2023-08-01-007170-a-c1 · procedure: reporting

  2. Contract

    Date 4 July 2023 · Amount UAH 435,000 · Buyer Lvivskyi derzhavnyi universytet vnutrishnikh sprav [08571995] · Supplier PrAT "Lvivoblenerho [00131587] · Ref UA-2023-07-05-014681-a-b1 · procedure: reporting

  3. Contract

    Date 23 December 2022 · Amount UAH 1,014,973 · Buyer Lvivskyi derzhavnyi universytet vnutrishnikh sprav [08571995] · Supplier PrAT "Lvivoblenerho [00131587] · Ref UA-2022-12-28-005602-a-b1 · procedure: reporting

  4. Contract

    Date 22 February 2022 · Amount UAH 1,773 · Buyer Lvivskyi derzhavnyi universytet vnutrishnikh sprav [08571995] · Supplier PrAT "Lvivoblenerho [00131587] · Ref UA-2022-02-24-003584-a-a1 · procedure: reporting

Other records of this company13

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 044 October 2026Findings · Duplicate records in the data
  5. 054 October 2026Findings · Contract splitting on one day
  6. 064 October 2026Findings · Large contract without a procedure
  7. 074 October 2026Findings · Large contract without a procedure
  8. 084 October 2026Findings · Large contract without a procedure
  9. 094 October 2026Findings · Large contract without a procedure
  10. 104 October 2026Findings · Large contract without a procedure
All 13
  1. 114 October 2026Findings · Large contract without a procedure
  2. 124 October 2026Findings · Large contract without a procedure
  3. 134 October 2026Findings · Large contract without a procedure

JSONFindings · Procurement plan published late