Ukraine · Findings · Procurement plan published late

PRYVATNE AKTSIONERNE TOVARYSTVO "OBUKHIVSKYI MOLOCHNYI ZAVOD" [00445914]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 27,788 UAH signed 2023-11-01…2023-11-01, and the procurement plan was created later — 2023-12-21 (to 50 days after the contract); plan UA-P-2023-12-21-006176-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
PRYVATNE AKTSIONERNE TOVARYSTVO "OBUKHIVSKYI MOLOCHNYI ZAVOD" [00445914]
EDRPOU code
00445914
Buyer
LITSEI «PERSHA BILOTSERKIVSKA HIMNAZIIA» BILOTSERKIVSKOI MISKOI RADY KYIVSKOI OBLASTI [22207457]
Indicator
Procurement plan published late
Amount
UAH 27,788
Records behind the indicator
1
Found
5 October 2026
Code
UA-2316609
Reference
2023-11-01
Reference
2023-12-21
Reference
UA-P-2023-12-21-006176-b

What stands behind it1

  1. Contract

    Date 1 November 2023 · Amount UAH 27,788 · Buyer LITSEI «PERSHA BILOTSERKIVSKA HIMNAZIIA» BILOTSERKIVSKOI MISKOI RADY KYIVSKOI OBLASTI [22207457] · Supplier PRYVATNE AKTSIONERNE TOVARYSTVO "OBUKHIVSKYI MOLOCHNYI ZAVOD [00445914] · Ref UA-2023-12-21-012123-a-b1 · procedure: reporting

Other records of this company11

  1. 014 October 2026Findings · Contract splitting on one day
  2. 024 October 2026Findings · Contract splitting on one day
  3. 034 October 2026Findings · Contract splitting on one day
  4. 044 October 2026Findings · Contract splitting under the threshold
  5. 054 October 2026Findings · Contract splitting under the threshold
  6. 064 October 2026Findings · Contract splitting under the threshold
  7. 074 October 2026Findings · Contract splitting under the threshold
  8. 084 October 2026Findings · Contract splitting under the threshold
  9. 094 October 2026Findings · Contract splitting under the threshold
  10. 104 October 2026Findings · Contract splitting under the threshold
All 11
  1. 114 October 2026Findings · Contract splitting under the threshold

Findings · Procurement plan published late