PRYVATNE AKTSIONERNE TOVARYSTVO "VOLYNOBLENERHO" [00131512]
Why it is here
Indicator “Procurement plan published late”: 2 contracts for 3,263,000 UAH signed 2024-12-16…2025-12-17, and the procurement plan was created later — 2024-12-17 (to 2 days after the contract); plan UA-P-2024-12-17-003889-a,UA-P-2025-12-19-002412-a.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- PRYVATNE AKTSIONERNE TOVARYSTVO "VOLYNOBLENERHO" [00131512]
- EDRPOU code
- 00131512
- Buyer
- Kamin-Kashyrske vyrobnyche upravlinnia zhytlovo-komunalnoho hospodarstva [03339360]
- Indicator
- Procurement plan published late
- Amount
- UAH 3,263,000
- Records behind the indicator
- 2
- Found
- 5 October 2026
- Code
- UA-2316362
- Reference
- 2024-12-16
- Reference
- 2025-12-17
- Reference
- 2024-12-17
- Reference
- UA-P-2024-12-17-003889-a
- Reference
- UA-P-2025-12-19-002412-a
What stands behind it2
Contract
Date 19 December 2025 · Amount UAH 1,703,000 · Buyer Kamin-Kashyrske vyrobnyche upravlinnia zhytlovo-komunalnoho hospodarstva [03339360] · Ref UA-2025-12-19-006510-a-a1 · procedure: reporting
Contract
Date 17 December 2024 · Amount UAH 1,560,000 · Buyer Kamin-Kashyrske vyrobnyche upravlinnia zhytlovo-komunalnoho hospodarstva [03339360] · Ref UA-2024-12-17-004840-a-a1 · procedure: reporting
Other records of this company18
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 045 October 2026Findings · Procurement plan published late
- 055 October 2026Findings · Procurement plan published late
- 065 October 2026Findings · Procurement plan published late
- 075 October 2026Findings · Procurement plan split into parts
- 085 October 2026Findings · Procurement plan split into parts
- 095 October 2026Findings · Procurement plan split into parts
- 105 October 2026Findings · Procurement plan split into parts
All 18
- 115 October 2026Findings · Procurement plan split into parts
- 124 October 2026Findings · Contract splitting on one day
- 134 October 2026Findings · Large contract without a procedure
- 144 October 2026Findings · Large contract without a procedure
- 154 October 2026Findings · Large contract without a procedure
- 164 October 2026Findings · Large contract without a procedure
- 174 October 2026Findings · Large contract without a procedure
- 184 October 2026Findings · Large contract without a procedure