Indicator “Procurement plan published late”: 2 contracts for 6,338,400 UAH signed 2023-12-22…2024-12-23, and the procurement plan was created later — 2023-12-25 (to 3 days after the contract); plan UA-P-2023-12-25-000570-c,UA-P-2024-12-25-007453-a.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- KOMUNALNYI KONTSERN "TSENTR KOMUNALNOHO SERVISU" [39946227]
- EDRPOU code
- 39946227
- Buyer
- KP Keruiucha kompaniia z obsluhovuvannia zhytlovoho fondu Pecherskoho raionu m. Kyieva [35692211]
- Indicator
- Procurement plan published late
- Amount
- UAH 6,338,400
- Records behind the indicator
- 2
- Found
- 5 October 2026
- Code
- UA-2308833
- Reference
- 2023-12-22
- Reference
- 2024-12-23
- Reference
- 2023-12-25
- Reference
- UA-P-2023-12-25-000570-c
- Reference
- UA-P-2024-12-25-007453-a
What stands behind it2
Contract
Date 25 December 2024 · Amount UAH 3,275,280 · Buyer KP Keruiucha kompaniia z obsluhovuvannia zhytlovoho fondu Pecherskoho raionu m. Kyieva [35692211] · Ref UA-2024-12-25-007026-a-b1 · procedure: reporting
Contract
Date 22 December 2023 · Amount UAH 3,137,040 · Buyer KP KOMUNALNE PIDPRYIEMSTVO "KERUIUCHA KOMPANIIA Z OBSLUHOVUVANNIA ZHYTLOVOHO FONDU PECHERSKOHO RAIONU M.KYIEVA [35692211] · Supplier KOMUNALNYI KONTSERN "TSENTR KOMUNALNOHO SERVISU [39946227] · Ref UA-2023-12-25-001077-a-a1 · procedure: reporting
Other records of this company18
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 045 October 2026Findings · Procurement plan published late
- 055 October 2026Findings · Procurement plan published late
- 065 October 2026Findings · Procurement plan published late
- 075 October 2026Findings · Procurement plan split into parts
- 085 October 2026Findings · Court decisions about the party
- 095 October 2026Findings · Court decisions about the party
- 104 October 2026Findings · Large contract without a procedure
All 18
- 114 October 2026Findings · Large contract without a procedure
- 124 October 2026Findings · Large contract without a procedure
- 134 October 2026Findings · Large contract without a procedure
- 144 October 2026Findings · Large contract without a procedure
- 154 October 2026Findings · Large contract without a procedure
- 164 October 2026Findings · Large contract without a procedure
- 174 October 2026Findings · Contract value inflated by amendments
- 184 October 2026Findings · Contract value inflated by amendments