Ukraine · Findings · Procurement plan published late
KOMUNALNE PIDPRYIEMSTVO "MISKTEPLOVODENERHIIA" [36588183]
Why it is here
Indicator “Procurement plan published late”: 3 contracts for 3,318,583 UAH signed 2022-02-21…2023-08-28, and the procurement plan was created later — 2022-02-23 (to 2 days after the contract); plan UA-P-2022-02-23-003569-a,UA-P-2022-12-23-004389-c,UA-P-2023-08-29-000567-a.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- KOMUNALNE PIDPRYIEMSTVO "MISKTEPLOVODENERHIIA" [36588183]
- EDRPOU code
- 36588183
- Buyer
- ZAKLAD VYSHCHOI OSVITY "PODILSKYI DERZHAVNYI UNIVERSYTET" [22769675]
- Indicator
- Procurement plan published late
- Amount
- UAH 3,318,583
- Records behind the indicator
- 3
- Found
- 5 October 2026
- Code
- UA-2308297
- Reference
- 2022-02-21
- Reference
- 2023-08-28
- Reference
- 2022-02-23
- Reference
- UA-P-2022-02-23-003569-a
- Reference
- UA-P-2022-12-23-004389-c
- Reference
- UA-P-2023-08-29-000567-a
What stands behind it3
Contract
Date 28 August 2023 · Amount UAH 2,997,002 · Buyer ZAKLAD VYSHCHOI OSVITY "PODILSKYI DERZHAVNYI UNIVERSYTET [22769675] · Supplier KOMUNALNE PIDPRYIEMSTVO "MISKTEPLOVODENERHIIA [36588183] · Ref UA-2023-08-29-006354-a-a1 · procedure: reporting
Contract
Date 22 December 2022 · Amount UAH 320,702 · Buyer ZAKLAD VYSHCHOI OSVITY "PODILSKYI DERZHAVNYI UNIVERSYTET [22769675] · Supplier KOMUNALNE PIDPRYIEMSTVO "MISKTEPLOVODENERHIIA [36588183] · Ref UA-2022-12-23-018364-a-c1 · procedure: reporting
Contract
Date 21 February 2022 · Amount UAH 880 · Buyer ZAKLAD VYSHCHOI OSVITY "PODILSKYI DERZHAVNYI UNIVERSYTET [22769675] · Supplier KOMUNALNE PIDPRYIEMSTVO "MISKTEPLOVODENERHIIA [36588183] · Ref UA-2022-02-23-003528-a-a1 · procedure: reporting
Other records of this company12
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan split into parts
- 035 October 2026Findings · Procurement plan split into parts
- 045 October 2026Findings · Several indicators on one party
- 054 October 2026Findings · Large contract without a procedure
- 064 October 2026Findings · Large contract without a procedure
- 074 October 2026Findings · Large contract without a procedure