Ukraine · Findings · Procurement plan published late
KOMUNALNE PIDPRYIEMSTVO "VINNYTSIAOBLTEPLOENERHO" [33649363]
Why it is here
Indicator “Procurement plan published late”: 3 contracts for 6,495,871 UAH signed 2022-12-08…2024-12-09, and the procurement plan was created later — 2022-12-10 (to 2 days after the contract); plan UA-P-2022-12-10-000734-c,UA-P-2022-12-10-000560-b,UA-P-2024-12-11-026005-a.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- KOMUNALNE PIDPRYIEMSTVO "VINNYTSIAOBLTEPLOENERHO" [33649363]
- EDRPOU code
- 33649363
- Buyer
- Komunalna ustanova "Oblasnyi pansionat dlia osib z invalidnistiu ta osib pokhyloho viku" [02770067]
- Indicator
- Procurement plan published late
- Amount
- UAH 6,495,871
- Records behind the indicator
- 3
- Found
- 5 October 2026
- Code
- UA-2307995
- Reference
- 2022-12-08
- Reference
- 2024-12-09
- Reference
- 2022-12-10
- Reference
- UA-P-2022-12-10-000734-c
- Reference
- UA-P-2022-12-10-000560-b
- Reference
- UA-P-2024-12-11-026005-a
What stands behind it3
Contract
Date 11 December 2024 · Amount UAH 1,888,557 · Buyer Komunalna ustanova "Oblasnyi pansionat dlia osib z invalidnistiu ta osib pokhyloho viku [02770067] · Ref UA-2024-12-11-021092-a-a1 · procedure: reporting
Contract
Date 8 December 2022 · Amount UAH 1,899,140 · Buyer Komunalna ustanova "Oblasnyi pansionat dlia osib z invalidnistiu ta osib pokhyloho viku [02770067] · Supplier KOMUNALNE PIDPRYIEMSTVO "VINNYTSIAOBLTEPLOENERHO [33649363] · Ref UA-2022-12-17-001413-a-a1 · procedure: reporting
Contract
Date 8 December 2022 · Amount UAH 2,708,174 · Buyer Komunalna ustanova "Oblasnyi pansionat dlia osib z invalidnistiu ta osib pokhyloho viku [02770067] · Supplier KOMUNALNE PIDPRYIEMSTVO "VINNYTSIAOBLTEPLOENERHO [33649363] · Ref UA-2022-12-17-001440-a-b1 · procedure: reporting
Other records of this company38
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 045 October 2026Findings · Procurement plan published late
- 055 October 2026Findings · Procurement plan published late
- 065 October 2026Findings · Procurement plan published late
- 075 October 2026Findings · Several indicators on one party
- 084 October 2026Findings · Duplicate records in the data
- 094 October 2026Findings · Duplicate records in the data
- 104 October 2026Findings · Duplicate records in the data
All 38
- 114 October 2026Findings · Duplicate records in the data
- 124 October 2026Findings · Duplicate records in the data
- 134 October 2026Findings · Duplicate records in the data
- 144 October 2026Findings · Duplicate records in the data
- 154 October 2026Findings · Duplicate records in the data
- 164 October 2026Findings · Large contract without a procedure
- 174 October 2026Findings · Large contract without a procedure
- 184 October 2026Findings · Large contract without a procedure
- 194 October 2026Findings · Large contract without a procedure
- 204 October 2026Findings · Large contract without a procedure
- 214 October 2026Findings · Large contract without a procedure
- 224 October 2026Findings · Large contract without a procedure
- 234 October 2026Findings · Large contract without a procedure
- 244 October 2026Findings · Large contract without a procedure
- 254 October 2026Findings · Large contract without a procedure
- 264 October 2026Findings · Large contract without a procedure
- 274 October 2026Findings · Large contract without a procedure
- 284 October 2026Findings · Large contract without a procedure
- 294 October 2026Findings · Large contract without a procedure
- 304 October 2026Findings · Large contract without a procedure
- 314 October 2026Findings · Large contract without a procedure
- 324 October 2026Findings · Large contract without a procedure
- 334 October 2026Findings · Large contract without a procedure
- 344 October 2026Findings · Large contract without a procedure
- 354 October 2026Findings · Large contract without a procedure
- 364 October 2026Findings · Large contract without a procedure
- 374 October 2026Findings · Large contract without a procedure
- 384 October 2026Findings · Link to the register of corruption offenders