Ukraine · Findings · Procurement plan published late
AT "DTEK DNIPROVSKI ELEKTROMEREZHI" [23359034]
Why it is here
Indicator “Procurement plan published late”: 3 contracts for 1,095,462 UAH signed 2023-03-15…2023-12-14, and the procurement plan was created later — 2023-03-20 (to 12 days after the contract); plan UA-P-2023-03-20-001501-a,UA-P-2023-03-20-003313-b,UA-P-2023-12-26-000425-a.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- AT "DTEK DNIPROVSKI ELEKTROMEREZHI" [23359034]
- EDRPOU code
- 23359034
- Buyer
- Pivdenne mizhrehionalne upravlinnia Ministerstva iustytsii (m. Odesa) [43315529]
- Indicator
- Procurement plan published late
- Amount
- UAH 1,095,462
- Records behind the indicator
- 3
- Found
- 5 October 2026
- Code
- UA-2301356
- Reference
- 2023-03-15
- Reference
- 2023-12-14
- Reference
- 2023-03-20
- Reference
- UA-P-2023-03-20-001501-a
- Reference
- UA-P-2023-03-20-003313-b
- Reference
- UA-P-2023-12-26-000425-a
What stands behind it3
Contract
Date 14 December 2023 · Amount UAH 1,698 · Buyer Pivdenne mizhrehionalne upravlinnia Ministerstva iustytsii (m. Odesa) [43315529] · Supplier AT "DTEK DNIPROVSKI ELEKTROMEREZHI [23359034] · Ref UA-2023-12-26-000926-a-a1 · procedure: reporting
Contract
Date 15 March 2023 · Amount UAH 1,087,764 · Buyer Pivdenne mizhrehionalne upravlinnia Ministerstva iustytsii (m. Odesa) [43315529] · Supplier AKTSIONERNE TOVARYSTVO «DTEK DNIPROVSKI ELEKTROMEREZHI [23359034] · Ref UA-2023-03-20-003981-a-b1 · procedure: reporting
Contract
Date 15 March 2023 · Amount UAH 6,000 · Buyer Pivdenne mizhrehionalne upravlinnia Ministerstva iustytsii (m. Odesa) [43315529] · Supplier AKTSIONERNE TOVARYSTVO «DTEK DNIPROVSKI ELEKTROMEREZHI [23359034] · Ref UA-2023-03-20-006719-a-c1 · procedure: reporting
Other records of this company16
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 044 October 2026Findings · Contract splitting on one day
- 054 October 2026Findings · Contract splitting on one day
- 064 October 2026Findings · Contract splitting on one day
- 074 October 2026Findings · Large contract without a procedure
- 084 October 2026Findings · Large contract without a procedure
- 094 October 2026Findings · Large contract without a procedure
- 104 October 2026Findings · Large contract without a procedure
All 16
- 114 October 2026Findings · Large contract without a procedure
- 124 October 2026Findings · Large contract without a procedure
- 134 October 2026Findings · Large contract without a procedure
- 144 October 2026Findings · Large contract without a procedure
- 154 October 2026Findings · Large contract without a procedure
- 164 October 2026Findings · Large contract without a procedure