Ukraine · Findings · Procurement plan published late
KHRYSTYNIVSKE VYROBNYCHE UPRAVLINNIA ZHYTLOVO-KOMUNALNOHO HOSPODARSTVA [03356996]
Why it is here
Indicator “Procurement plan published late”: 3 contracts for 9,443 UAH signed 2022-04-25…2023-11-27, and the procurement plan was created later — 2022-04-27 (to 34 days after the contract); plan UA-P-2022-04-27-002356-a,UA-P-2022-12-23-000069-a,UA-P-2023-12-31-000334-b.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- KHRYSTYNIVSKE VYROBNYCHE UPRAVLINNIA ZHYTLOVO-KOMUNALNOHO HOSPODARSTVA [03356996]
- EDRPOU code
- 03356996
- Buyer
- HOLOVNE UPRAVLINNIA NATSIONALNOI POLITSII V CHERKASKII OBLASTI [40108667]
- Indicator
- Procurement plan published late
- Amount
- UAH 9,443
- Records behind the indicator
- 3
- Found
- 5 October 2026
- Code
- UA-2299230
- Reference
- 2022-04-25
- Reference
- 2023-11-27
- Reference
- 2022-04-27
- Reference
- UA-P-2022-04-27-002356-a
- Reference
- UA-P-2022-12-23-000069-a
- Reference
- UA-P-2023-12-31-000334-b
What stands behind it3
Contract
Date 27 November 2023 · Amount UAH 3,510 · Buyer HOLOVNE UPRAVLINNIA NATSIONALNOI POLITSII V CHERKASKII OBLASTI [40108667] · Supplier KHRYSTYNIVSKE VYROBNYCHE UPRAVLINNIA ZHYTLOVO-KOMUNALNOHO HOSPODARSTVA [03356996] · Ref UA-2023-12-31-001028-a-c1 · procedure: reporting
Contract
Date 21 December 2022 · Amount UAH 129 · Buyer HOLOVNE UPRAVLINNIA NATSIONALNOI POLITSII V CHERKASKII OBLASTI [40108667] · Supplier KHRYSTYNIVSKE VYROBNYCHE UPRAVLINNIA ZHYTLOVO-KOMUNALNOHO HOSPODARSTVA [03356996] · Ref UA-2022-12-23-000260-a-b1 · procedure: reporting
Contract
Date 25 April 2022 · Amount UAH 5,804 · Buyer HOLOVNE UPRAVLINNIA NATSIONALNOI POLITSII V CHERKASKII OBLASTI [40108667] · Supplier KHRYSTYNIVSKE VYROBNYCHE UPRAVLINNIA ZHYTLOVO-KOMUNALNOHO HOSPODARSTVA [03356996] · Ref UA-2022-04-27-002666-a-a1 · procedure: reporting
Other records of this company13
- 015 October 2026Findings · Procurement plan split into parts
- 025 October 2026Findings · Procurement plan split into parts
- 035 October 2026Findings · Procurement plan split into parts
- 045 October 2026Findings · Procurement plan split into parts
- 055 October 2026Findings · Procurement plan split into parts
- 065 October 2026Findings · Procurement plan split into parts
- 075 October 2026Findings · Procurement plan split into parts
- 085 October 2026Findings · Procurement plan split into parts
- 095 October 2026Findings · Procurement plan split into parts
- 105 October 2026Findings · Procurement plan split into parts