WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

Upravlinnia politsii okhorony v Ternopilskii oblasti [40108819]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 2,859,950 UAH signed 2025-12-30…2025-12-30, and the procurement plan was created later — 2025-12-31 (to 1 days after the contract); plan UA-P-2025-12-31-007090-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Upravlinnia politsii okhorony v Ternopilskii oblasti [40108819]
EDRPOU code
40108819
Buyer
KP Upravlinnia z ekspluatatsii mainovoho kompleksu Ternopilskoi oblasnoi rady [30165302]
Indicator
Procurement plan published late
Amount
UAH 2,859,950
Records behind the indicator
1
Found
5 October 2026
Code
UA-2295680
Reference
2025-12-30
Reference
2025-12-31
Reference
UA-P-2025-12-31-007090-a

What stands behind it1

  1. Contract

    Date 31 December 2025 · Amount UAH 2,859,950 · Buyer KP Upravlinnia z ekspluatatsii mainovoho kompleksu Ternopilskoi oblasnoi rady [30165302] · Ref UA-2025-12-31-006135-a-a1 · procedure: reporting

Other records of this company12

  1. 015 October 2026Findings · Procurement plan split into parts
  2. 025 October 2026Findings · Court decisions about the party
  3. 035 October 2026Findings · Court decisions about the party
  4. 045 October 2026Findings · Several indicators on one party
  5. 054 October 2026Findings · Duplicate records in the data
  6. 064 October 2026Findings · Contract splitting under the threshold
  7. 074 October 2026Findings · Contract splitting under the threshold
  8. 084 October 2026Findings · Cartel pattern
  9. 094 October 2026Findings · Cartel pattern
  10. 104 October 2026Findings · Cartel pattern
All 12
  1. 114 October 2026Findings · Cartel pattern
  2. 124 October 2026Findings · Cartel pattern

JSONFindings · Procurement plan published late