Indicator “Procurement plan published late”: 3 contracts for 15,588,713 UAH signed 2023-03-07…2024-12-27, and the procurement plan was created later — 2023-03-21 (to 14 days after the contract); plan UA-P-2023-03-21-000682-a,UA-P-2023-03-21-003904-b,UA-P-2024-12-29-001380-a.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "DINATRON - HRUP" [43371363]
- EDRPOU code
- 43371363
- Buyer
- Komunalne nekomertsiine pidpryiemstvo «Miska likarnia №9» Zaporizkoi miskoi rady [05498694]
- Indicator
- Procurement plan published late
- Amount
- UAH 15,588,713
- Records behind the indicator
- 3
- Found
- 5 October 2026
- Code
- UA-2293089
- Reference
- 2023-03-07
- Reference
- 2024-12-27
- Reference
- 2023-03-21
- Reference
- UA-P-2023-03-21-000682-a
- Reference
- UA-P-2023-03-21-003904-b
- Reference
- UA-P-2024-12-29-001380-a
What stands behind it3
Contract
Date 30 December 2024 · Amount UAH 1,792,470 · Buyer Komunalne nekomertsiine pidpryiemstvo «Miska likarnia №9» Zaporizkoi miskoi rady [05498694] · Ref UA-2024-12-30-003599-a-c1 · procedure: reporting
Contract
Date 8 March 2023 · Amount UAH 7,633,439 · Buyer KP "Miska likarnia №9" Zaporizkoi miskoi rady [05498694] · Supplier TOV "Dinatron-Hrup [43371363] · Ref UA-2023-03-21-001961-a-a1 · procedure: reporting
Contract
Date 7 March 2023 · Amount UAH 6,162,803 · Buyer KP "Miska likarnia №9" Zaporizkoi miskoi rady [05498694] · Supplier TOV "Dinatron-Hrup [43371363] · Ref UA-2023-03-21-007728-a-b1 · procedure: reporting
Other records of this company7
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 044 October 2026Findings · Contract splitting on one day
- 054 October 2026Findings · Contract splitting under the threshold
- 064 October 2026Findings · Contract splitting under the threshold
- 074 October 2026Findings · Contract splitting under the threshold