Ukraine · Findings · Procurement plan published late

KOMUNALNE PIDPRYIEMSTVO "TEPLOPOSTACHANNIA MISTA ODEUY" [34674102]

Why it is here

Indicator “Procurement plan published late”: 2 contracts for 3,471,168 UAH signed 2023-12-14…2023-12-27, and the procurement plan was created later — 2023-12-15 (to 1 days after the contract); plan UA-P-2023-12-15-004769-a,UA-P-2023-12-28-000852-c.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
KOMUNALNE PIDPRYIEMSTVO "TEPLOPOSTACHANNIA MISTA ODEUY" [34674102]
EDRPOU code
34674102
Buyer
Odeskyi derzhavnyi ekolohichnyi universytet [26134086]
Indicator
Procurement plan published late
Amount
UAH 3,471,168
Records behind the indicator
2
Found
5 October 2026
Code
UA-2287320
Reference
2023-12-14
Reference
2023-12-27
Reference
2023-12-15
Reference
UA-P-2023-12-15-004769-a
Reference
UA-P-2023-12-28-000852-c

What stands behind it2

  1. Contract

    Date 27 December 2023 · Amount UAH 2,641,990 · Buyer Odeskyi derzhavnyi ekolohichnyi universytet [26134086] · Supplier KOMUNALNE PIDPRYIEMSTVO "TEPLOPOSTACHANNIA MISTA ODESY [34674102] · Ref UA-2023-12-28-002057-a-c1 · procedure: reporting

  2. Contract

    Date 14 December 2023 · Amount UAH 829,178 · Buyer Odeskyi derzhavnyi ekolohichnyi universytet [26134086] · Supplier KOMUNALNE PIDPRYIEMSTVO "TEPLOPOSTACHANNIA MISTA ODESY [34674102] · Ref UA-2023-12-15-012806-a-c1 · procedure: reporting

Other records of this company29

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 075 October 2026Findings · Procurement plan published late
  8. 085 October 2026Findings · Procurement plan published late
  9. 094 October 2026Findings · Duplicate records in the data
  10. 104 October 2026Findings · Contract splitting on one day
All 29
  1. 114 October 2026Findings · Large contract without a procedure
  2. 124 October 2026Findings · Large contract without a procedure
  3. 134 October 2026Findings · Large contract without a procedure
  4. 144 October 2026Findings · Large contract without a procedure
  5. 154 October 2026Findings · Large contract without a procedure
  6. 164 October 2026Findings · Large contract without a procedure
  7. 174 October 2026Findings · Large contract without a procedure
  8. 184 October 2026Findings · Large contract without a procedure
  9. 194 October 2026Findings · Large contract without a procedure
  10. 204 October 2026Findings · Large contract without a procedure
  11. 214 October 2026Findings · Large contract without a procedure
  12. 224 October 2026Findings · Large contract without a procedure
  13. 234 October 2026Findings · Large contract without a procedure
  14. 244 October 2026Findings · Large contract without a procedure
  15. 254 October 2026Findings · Large contract without a procedure
  16. 264 October 2026Findings · Large contract without a procedure
  17. 274 October 2026Findings · Large contract without a procedure
  18. 284 October 2026Findings · Large contract without a procedure
  19. 294 October 2026Findings · Large contract without a procedure

JSONFindings · Procurement plan published late