WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

DERZHAVNE PIDPRYIEMSTVO KYIVSKA OFSETNA FABRYKA [05450185]

Why it is here

Indicator “Procurement plan published late”: 2 contracts for 7,902 UAH signed 2022-05-04…2022-05-25, and the procurement plan was created later — 2022-12-29 (to 239 days after the contract); plan UA-P-2022-12-29-000867-b,UA-P-2022-12-29-000610-c.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
DERZHAVNE PIDPRYIEMSTVO KYIVSKA OFSETNA FABRYKA [05450185]
EDRPOU code
05450185
Buyer
NOVOVOLYNSKA MISKA DERZHAVNA LIKARNIA VETERYNARNOI MEDYTSYNY [00692624]
Indicator
Procurement plan published late
Amount
UAH 7,902
Records behind the indicator
2
Found
5 October 2026
Code
UA-2286511
Reference
2022-05-04
Reference
2022-05-25
Reference
2022-12-29
Reference
UA-P-2022-12-29-000867-b
Reference
UA-P-2022-12-29-000610-c

What stands behind it2

  1. Contract

    Date 25 May 2022 · Amount UAH 6,351 · Buyer NOVOVOLYNSKA MISKA DERZHAVNA LIKARNIA VETERYNARNOI MEDYTSYNY [00692624] · Supplier DERZHAVNE PIDPRYIEMSTVO KYIVSKA OFSETNA FABRYKA [05450185] · Ref UA-2022-12-29-001996-a-a1 · procedure: reporting

  2. Contract

    Date 4 May 2022 · Amount UAH 1,551 · Buyer NOVOVOLYNSKA MISKA DERZHAVNA LIKARNIA VETERYNARNOI MEDYTSYNY [00692624] · Supplier DERZHAVNE PIDPRYIEMSTVO KYIVSKA OFSETNA FABRYKA [05450185] · Ref UA-2022-12-29-001849-a-a1 · procedure: reporting

Other records of this company6

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 064 October 2026Findings · Contract splitting under the threshold

Findings · Procurement plan published late