Ukraine · Findings · Procurement plan published late
AT "UKRPOSHTA" [21560045]
Why it is here
Indicator “Procurement plan published late”: 1 contracts for 3,108,150 UAH signed 2023-12-27…2023-12-27, and the procurement plan was created later — 2023-12-28 (to 1 days after the contract); plan UA-P-2023-12-28-001259-c.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- AT "UKRPOSHTA" [21560045]
- EDRPOU code
- 21560045
- Buyer
- Aktsionerne tovarystvo Kyivhaz [03346331]
- Indicator
- Procurement plan published late
- Amount
- UAH 3,108,150
- Records behind the indicator
- 1
- Found
- 5 October 2026
- Code
- UA-2285470
- Reference
- 2023-12-27
- Reference
- 2023-12-28
- Reference
- UA-P-2023-12-28-001259-c
What stands behind it1
Contract
Date 27 December 2023 · Amount UAH 3,108,303 · Buyer Aktsionerne tovarystvo Kyivhaz [03346331] · Supplier AT "UKRPOSHTA [21560045] · Ref UA-2023-12-28-003113-a-c1 · procedure: reporting
Other records of this company55
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 045 October 2026Findings · Procurement plan published late
- 055 October 2026Findings · Procurement plan published late
- 065 October 2026Findings · Procurement plan published late
- 075 October 2026Findings · Procurement plan published late
- 085 October 2026Findings · Procurement plan published late
- 095 October 2026Findings · Procurement plan published late
- 105 October 2026Findings · Procurement plan published late
All 55
- 115 October 2026Findings · Procurement plan published late
- 125 October 2026Findings · Procurement plan published late
- 135 October 2026Findings · Procurement plan split into parts
- 145 October 2026Findings · Procurement plan split into parts
- 155 October 2026Findings · Procurement plan split into parts
- 165 October 2026Findings · Procurement plan split into parts
- 175 October 2026Findings · Procurement plan split into parts
- 184 October 2026Findings · Duplicate records in the data
- 194 October 2026Findings · Duplicate records in the data
- 204 October 2026Findings · Duplicate records in the data
- 214 October 2026Findings · Duplicate records in the data
- 224 October 2026Findings · Contract splitting on one day
- 234 October 2026Findings · Contract splitting on one day
- 244 October 2026Findings · Contract splitting on one day
- 254 October 2026Findings · Contract splitting on one day
- 264 October 2026Findings · Large contract without a procedure
- 274 October 2026Findings · Large contract without a procedure
- 284 October 2026Findings · Large contract without a procedure
- 294 October 2026Findings · Large contract without a procedure
- 304 October 2026Findings · Large contract without a procedure
- 314 October 2026Findings · Large contract without a procedure
- 324 October 2026Findings · Large contract without a procedure
- 334 October 2026Findings · Large contract without a procedure
- 344 October 2026Findings · Large contract without a procedure
- 354 October 2026Findings · Large contract without a procedure
- 364 October 2026Findings · Large contract without a procedure
- 374 October 2026Findings · Large contract without a procedure
- 384 October 2026Findings · Large contract without a procedure
- 394 October 2026Findings · Large contract without a procedure
- 404 October 2026Findings · Large contract without a procedure
- 414 October 2026Findings · Large contract without a procedure
- 424 October 2026Findings · Large contract without a procedure
- 434 October 2026Findings · Large contract without a procedure
- 444 October 2026Findings · Large contract without a procedure
- 454 October 2026Findings · Large contract without a procedure
- 464 October 2026Findings · Large contract without a procedure
- 474 October 2026Findings · Large contract without a procedure
- 484 October 2026Findings · Large contract without a procedure
- 494 October 2026Findings · Large contract without a procedure
- 504 October 2026Findings · Large contract without a procedure
- 514 October 2026Findings · Large contract without a procedure
- 524 October 2026Findings · Contract splitting under the threshold
- 534 October 2026Findings · Contract splitting under the threshold
- 544 October 2026Findings · Court decisions about the party
- 554 October 2026Findings · Contract value inflated by amendments