TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "TEPLO UKRAINA" [39355288]
Why it is here
Indicator “Duplicate records in the data”: 2 different contracts for one amount 3,338,247.74 UAH between the same parties (2 dates, the latest 2025-12-01); beyond one — 3,338,248 UAH.
The same payment or contract appears more than once in the published data. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "TEPLO UKRAINA" [39355288]
- EDRPOU code
- 39355288
- Buyer
- KOMUNALNE NEKOMERTSIINE PIDPRYIEMSTVO "ZVIAHELSKA BAHATOPROFILNA LIKARNIA" ZVIAHELSKOI MISKOI RADY [01991820] · 3,338,247.74 hrn
- Indicator
- Duplicate records in the data
- Amount
- UAH 3,338,248
- Records behind the indicator
- 2
- Found
- 4 October 2026
- Code
- UA-293193
- Reference
- 2025-12-01
What stands behind it2
Contract
Date 1 December 2025 · Amount UAH 3,338,248 · Buyer KOMUNALNE NEKOMERTSIINE PIDPRYIEMSTVO "ZVIAHELSKA BAHATOPROFILNA LIKARNIA" ZVIAHELSKOI MISKOI RADY [01991820] · Ref UA-2025-12-01-014601-a-b1 · procedure: reporting
Contract
Date 26 November 2025 · Amount UAH 3,338,248 · Buyer KOMUNALNE NEKOMERTSIINE PIDPRYIEMSTVO "ZVIAHELSKA BAHATOPROFILNA LIKARNIA" ZVIAHELSKOI MISKOI RADY [01991820] · Ref UA-2025-11-26-005916-a-a1 · procedure: reporting
Other records of this company12
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 044 October 2026Findings · Large contract without a procedure
- 054 October 2026Findings · Large contract without a procedure
- 064 October 2026Findings · Large contract without a procedure
- 074 October 2026Findings · Large contract without a procedure
- 084 October 2026Findings · Large contract without a procedure
- 094 October 2026Findings · Large contract without a procedure
- 104 October 2026Findings · Tax debtor receives a public contract