Canada · Findings · Federal infrastructure money: projects past their end date

Penticton, City of

Why it is here

Indicator “Federal infrastructure money: projects past their end date”: 4 projects overdue, federal contribution 5,243,537 $, oldest deadline 2023-09-01.

Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Penticton, City of
Buyer
BC
Indicator
Federal infrastructure money: projects past their end date
Amount
CAD 5,243,537
Records behind the indicator
4
Found
3 October 2026
Code
K-00504
Reference
2023-09-01

What stands behind it4

  1. Infrastructure project

    Penticton - Ellis #4 Dam Upgrade

    Date 19 September 2023 · Buyer Green Infrastructure Stream · Ref 67758

  2. Infrastructure project

    Penticton - Community Recreation Centre Energy Optimization

    Date 14 April 2023 · Buyer Green Infrastructure Stream · Ref 66994

  3. Infrastructure project

    City of Penticton Lake to Lake Bike Route - Final Section

    Date 21 December 2022 · Buyer Active Transportation Fund · Ref 63542

  4. Infrastructure project

    Penticton - Electric Vehicle Rapid Charging Infrastructure

    Date 9 February 2022 · Buyer Green Infrastructure Stream · Ref 62093