WORLDWIDE‑CORRUPTION

Canada · Findings · Federal infrastructure money: projects past their end date

Northwest Territories Power Corporation (NTPC)

Why it is here

Indicator “Federal infrastructure money: projects past their end date”: 2 projects overdue, federal contribution 25,301,250 $, oldest deadline 2023-08-31.

Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Northwest Territories Power Corporation (NTPC)
Buyer
NT
Indicator
Federal infrastructure money: projects past their end date
Amount
CAD 25,301,250
Records behind the indicator
2
Found
3 October 2026
Code
K-00456
Reference
2023-08-31

What stands behind it2

  1. Infrastructure project

    Taltson Hydroelectric Facility – Major Overhaul

    Date 9 August 2019 · Buyer Green Infrastructure Stream · Ref 54295

  2. Infrastructure project

    New Diesel Power Plant Construction in Sachs Harbour

    Date 26 November 2018 · Buyer Arctic Energy Fund · Ref 52953

JSONFindings · Federal infrastructure money: projects past their end date