Indonesia Competition Commission (KPPU) · Bid rigging in a tender (Article 22, Law 5/1999): 670
Page 1 of 2
1 2
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 26 January 2026 · case 03/KPPU-L/2025 · TENDER PEMBANGUNAN GEDUNG RUMAH SAKIT KABUPATEN BOGOR, KELURAHAN COGREG, KECAMATAN PARUNG, KABUPATEN BOGOR (BANPROV) TAHUN ANGGARAN 2021 · fine IDR 2,000,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Permata Anugerah Yalapersada
Authority Indonesia Competition Commission (KPPU) · From 26 January 2026 · case 03/KPPU-L/2025 · TENDER PEMBANGUNAN GEDUNG RUMAH SAKIT KABUPATEN BOGOR, KELURAHAN COGREG, KECAMATAN PARUNG, KABUPATEN BOGOR (BANPROV) TAHUN ANGGARAN 2021 · fine IDR 1,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 December 2025 · case 07/KPPU-L/2025 · TENDER PEMELIHARAAN MESIN INDUK MTU DI DITJEN BEA DAN CUKAI TAHUN 2024 · fine IDR 1,000,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Rolls Royce Solutions Indonesia
Authority Indonesia Competition Commission (KPPU) · From 29 December 2025 · case 07/KPPU-L/2025 · TENDER PEMELIHARAAN MESIN INDUK MTU DI DITJEN BEA DAN CUKAI TAHUN 2024 · fine IDR 1,500,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 28 July 2025 · case 17/KPPU-L/2024 · PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN JEMBATAN SINTONG KABUPATEN ROKAN HILIR TAHUN ANGGARAN 2023 · fine IDR 1,000,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 28 July 2025 · case 17/KPPU-L/2024 · PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN JEMBATAN SINTONG KABUPATEN ROKAN HILIR TAHUN ANGGARAN 2023 · barred from tenders for 2 years (Provinsi Riau) · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 28 July 2025 · case 17/KPPU-L/2024 · PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN JEMBATAN SINTONG KABUPATEN ROKAN HILIR TAHUN ANGGARAN 2023 · barred from tenders for 2 years (Provinsi Riau) · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 28 July 2025 · case 17/KPPU-L/2024 · PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN JEMBATAN SINTONG KABUPATEN ROKAN HILIR TAHUN ANGGARAN 2023 · barred from tenders for 2 years (Provinsi Riau) · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 July 2025 · case 14/KPPU-L/2024 · PENGADAAN TRANSPORTASI DARAT UNTUK PEMASOKAN ELECTRIC MULTIPLE UNIT (EMU) UNTUK PROYEK JAKARTA BANDUNG HIGH SPEED RAILWAYS PROJECT · fine IDR 2,000,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Anugerah Logistik Prestasindo
Authority Indonesia Competition Commission (KPPU) · From 22 July 2025 · case 14/KPPU-L/2024 · PENGADAAN TRANSPORTASI DARAT UNTUK PEMASOKAN ELECTRIC MULTIPLE UNIT (EMU) UNTUK PROYEK JAKARTA BANDUNG HIGH SPEED RAILWAYS PROJECT · fine IDR 2,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Perusahaan Umum Daerah (PERUMDA) Air Minum Amerta Dayan Gunung
Authority Indonesia Competition Commission (KPPU) · From 30 June 2025 · case 11/KPPU-L/2024 · PENGADAAN BADAN USAHA PENYEDIA AIR BERSIH DENGAN TEKNOLOGI SWRO (PRAKARSA BADAN USAHA) PADA PERUSAHAAN DAERAH AIR MINUM (PDAM) KABUPATEN LOMBOK UTARA TAHUN ANGGARAN 2017 · fine IDR 8,000,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 June 2025 · case 11/KPPU-L/2024 · PENGADAAN BADAN USAHA PENYEDIA AIR BERSIH DENGAN TEKNOLOGI SWRO (PRAKARSA BADAN USAHA) PADA PERUSAHAAN DAERAH AIR MINUM (PDAM) KABUPATEN LOMBOK UTARA TAHUN ANGGARAN 2017 · fine IDR 4,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 10 December 2024 · case 02/KPPU-L/2024 · PENGADAAN CRYO-EM, TRANSMISSION ELECTRON MICROSCOPE (TEM) ROOM TEMPERATURE FOR LIFE SCIENCE DAN TRANSMISSION ELECTRON MICROSCOPE (TEM) FOR MATERIAL SCIENCE PADA SATUAN KERJA DEPUTI BIDANG INFRASTRUKTUR RISET DAN INOVASI, BADAN RISET DAN INOVASI NASIONAL TAHUN ANGGARAN 2022 · fine IDR 1,000,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 10 December 2024 · case 02/KPPU-L/2024 · PENGADAAN CRYO-EM, TRANSMISSION ELECTRON MICROSCOPE (TEM) ROOM TEMPERATURE FOR LIFE SCIENCE DAN TRANSMISSION ELECTRON MICROSCOPE (TEM) FOR MATERIAL SCIENCE PADA SATUAN KERJA DEPUTI BIDANG INFRASTRUKTUR RISET DAN INOVASI, BADAN RISET DAN INOVASI NASIONAL TAHUN ANGGARAN 2022 · fine IDR 28,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 September 2024 · case 18/KPPU-L/2023 · PENGADAAN PEKERJAAN KONSTRUKSI PADA SATUAN KERJA UNIT PENYELENGGARA PELABUHAN KELAS II NUSA PENIDA KEMENTERIAN PERHUBUNGAN TAHUN ANGGARAN 2022 · fine IDR 1,500,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 September 2024 · case 18/KPPU-L/2023 · PENGADAAN PEKERJAAN KONSTRUKSI PADA SATUAN KERJA UNIT PENYELENGGARA PELABUHAN KELAS II NUSA PENIDA KEMENTERIAN PERHUBUNGAN TAHUN ANGGARAN 2022 · barred from tenders for 1 year · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 September 2024 · case 18/KPPU-L/2023 · PENGADAAN PEKERJAAN KONSTRUKSI PADA SATUAN KERJA UNIT PENYELENGGARA PELABUHAN KELAS II NUSA PENIDA KEMENTERIAN PERHUBUNGAN TAHUN ANGGARAN 2022 · barred from tenders for 1 year · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 September 2024 · case 18/KPPU-L/2023 · PENGADAAN PEKERJAAN KONSTRUKSI PADA SATUAN KERJA UNIT PENYELENGGARA PELABUHAN KELAS II NUSA PENIDA KEMENTERIAN PERHUBUNGAN TAHUN ANGGARAN 2022 · barred from tenders for 1 year · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 8 December 2023 · case 15-KPPU-L-2023 · PENGADAAN PEKERJAAN KONSTRUKSI PENINGKATAN JALAN KANDANG RODA-PAKANSARI KABUPATEN BOGOR TAHUN ANGGARAN 2021 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 8 December 2023 · case 15-KPPU-L-2023 · PENGADAAN PEKERJAAN KONSTRUKSI PENINGKATAN JALAN KANDANG RODA-PAKANSARI KABUPATEN BOGOR TAHUN ANGGARAN 2021 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 December 2023 · case 08/KPPU-L/2023 · PENGADAAN PAKET PEKERJAAN PENINGKATAN JALAN PEUREULAK-LOKOP-BATAS GAYO LUES (P.035.11) (SEGMEN 3) (MYC) DI PROVINSI ACEH TAHUN ANGGARAN 2020-2022 · fine IDR 1,500,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 December 2023 · case 08/KPPU-L/2023 · PENGADAAN PAKET PEKERJAAN PENINGKATAN JALAN PEUREULAK-LOKOP-BATAS GAYO LUES (P.035.11) (SEGMEN 3) (MYC) DI PROVINSI ACEH TAHUN ANGGARAN 2020-2022 · fine IDR 1,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 December 2023 · case 08/KPPU-L/2023 · PENGADAAN PAKET PEKERJAAN PENINGKATAN JALAN PEUREULAK-LOKOP-BATAS GAYO LUES (P.035.11) (SEGMEN 3) (MYC) DI PROVINSI ACEH TAHUN ANGGARAN 2020-2022 · fine IDR 1,900,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 December 2023 · case 08/KPPU-L/2023 · PENGADAAN PAKET PEKERJAAN PENINGKATAN JALAN PEUREULAK-LOKOP-BATAS GAYO LUES (P.035.11) (SEGMEN 3) (MYC) DI PROVINSI ACEH TAHUN ANGGARAN 2020-2022 · fine IDR 1,000,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 August 2023 · case 18/KPPU-L/2022 · PENGADAAN PEKERJAAN PEMBANGUNAN SISTEM PERSINYALAN ELEKTRIK JALUR GANDA KERETA API LINTAS BOGOR – CICURUG PADA SATUAN KERJA BALAI TEKNIK PERKERETAAPIAN WILAYAH JAWA BAGIAN BARAT KEMENTERIAN PERHUBUNGAN TAHUN ANGGARAN 2019-2021 (KODE TENDER 59035114) · fine IDR 6,058,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 August 2023 · case 18/KPPU-L/2022 · PENGADAAN PEKERJAAN PEMBANGUNAN SISTEM PERSINYALAN ELEKTRIK JALUR GANDA KERETA API LINTAS BOGOR – CICURUG PADA SATUAN KERJA BALAI TEKNIK PERKERETAAPIAN WILAYAH JAWA BAGIAN BARAT KEMENTERIAN PERHUBUNGAN TAHUN ANGGARAN 2019-2021 (KODE TENDER 59035114) · fine IDR 4,915,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Jakarta Propertindo (Perseroda)
Authority Indonesia Competition Commission (KPPU) · From 18 July 2023 · case 17/KPPU-L/2022 · PENGADAAN PEKERJAAN PELAKSANAAN PROYEK REVITALISASI PUSAT KESENIAN JAKARTA TAMAN ISMAIL MARZUKI TAHAP III · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Pembangunan Perumahan (Persero), Tbk
Authority Indonesia Competition Commission (KPPU) · From 18 July 2023 · case 17/KPPU-L/2022 · PENGADAAN PEKERJAAN PELAKSANAAN PROYEK REVITALISASI PUSAT KESENIAN JAKARTA TAMAN ISMAIL MARZUKI TAHAP III · fine IDR 16,800,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Jaya Konstruksi Manggala Pratama, Tbk
Authority Indonesia Competition Commission (KPPU) · From 18 July 2023 · case 17/KPPU-L/2022 · PENGADAAN PEKERJAAN PELAKSANAAN PROYEK REVITALISASI PUSAT KESENIAN JAKARTA TAMAN ISMAIL MARZUKI TAHAP III · fine IDR 11,200,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 25 January 2022 · case 25/KPPU-I/2020 · PENGADAAN PAKET PEMBANGUNAN REVETMENT DAN PENGURUGAN LAHAN DI PELABUHAN PERIKANAN POPOH KABUPATEN TULUNGAGUNG TAHUN ANGGARAN 2017 · fine IDR 2,700,000,000 · barred from tenders for 1 year (Indonesia) · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 25 January 2022 · case 25/KPPU-I/2020 · PENGADAAN PAKET PEMBANGUNAN REVETMENT DAN PENGURUGAN LAHAN DI PELABUHAN PERIKANAN POPOH KABUPATEN TULUNGAGUNG TAHUN ANGGARAN 2017 · barred from tenders for 1 year (Indonesia) · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 25 January 2022 · case 25/KPPU-I/2020 · PENGADAAN PAKET PEMBANGUNAN REVETMENT DAN PENGURUGAN LAHAN DI PELABUHAN PERIKANAN POPOH KABUPATEN TULUNGAGUNG TAHUN ANGGARAN 2017 · barred from tenders for 1 year (Indonesia) · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 25 January 2022 · case 25/KPPU-I/2020 · PENGADAAN PAKET PEMBANGUNAN REVETMENT DAN PENGURUGAN LAHAN DI PELABUHAN PERIKANAN POPOH KABUPATEN TULUNGAGUNG TAHUN ANGGARAN 2017 · barred from tenders for 1 year (Indonesia) · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 December 2021 · case 35/KPPU-I/2020 · PENGADAAN PAKET PEKERJAAN KONSTRUKSI JALAN (PROGRAM PERCEPATAN) PAKET 3 (PELANGAN-SP. PENGANTAP 3) DAN PAKET 4 (PELANGAN-SP. PENGANTAP 4) PADA SATKER DINAS PEKERJAAN UMUM DAN PENATAAN RUANG PROPINSI NUSA TENGGARA BARAT APBD TAHUN ANGGARAN 2017-2018 · fine IDR 1,359,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 December 2021 · case 35/KPPU-I/2020 · PENGADAAN PAKET PEKERJAAN KONSTRUKSI JALAN (PROGRAM PERCEPATAN) PAKET 3 (PELANGAN-SP. PENGANTAP 3) DAN PAKET 4 (PELANGAN-SP. PENGANTAP 4) PADA SATKER DINAS PEKERJAAN UMUM DAN PENATAAN RUANG PROPINSI NUSA TENGGARA BARAT APBD TAHUN ANGGARAN 2017-2018 · fine IDR 1,149,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 16 November 2021 · case 32/KPPU-I/2020 · PENGADAAN PAKET PEKERJAAN JALAN SEI SAREN – TELUK NILAU – SENYERANG – BTS. RIAU DI LINGKUNGAN DINAS PEKERJAAN UMUM DAN PERUMAHAN RAKYAT PEMERINTAH DAERAH PROVINSI JAMBI APBD TAHUN ANGGARAN 2017 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 16 November 2021 · case 32/KPPU-I/2020 · PENGADAAN PAKET PEKERJAAN JALAN SEI SAREN – TELUK NILAU – SENYERANG – BTS. RIAU DI LINGKUNGAN DINAS PEKERJAAN UMUM DAN PERUMAHAN RAKYAT PEMERINTAH DAERAH PROVINSI JAMBI APBD TAHUN ANGGARAN 2017 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 24 August 2021 · case 36/KPPU-I/2020 · LARANGAN PRAKTEK MONOPOLI DAN/ATAU PERSAINGAN USAHA TIDAK SEHAT (UNDANG-UNDANG NOMOR 5 TAHUN 1999) TERKAIT PENGADAAN PAKET REHABILITASI DAN RENOVASI SARANA DAN PRASARANA SEKOLAH KABUPATEN INDRAGIRI HILIR 1 DAN 2 APBN TAHUN ANGGARAN 2019 · fine IDR 2,050,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 24 August 2021 · case 36/KPPU-I/2020 · LARANGAN PRAKTEK MONOPOLI DAN/ATAU PERSAINGAN USAHA TIDAK SEHAT (UNDANG-UNDANG NOMOR 5 TAHUN 1999) TERKAIT PENGADAAN PAKET REHABILITASI DAN RENOVASI SARANA DAN PRASARANA SEKOLAH KABUPATEN INDRAGIRI HILIR 1 DAN 2 APBN TAHUN ANGGARAN 2019 · fine IDR 1,980,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 19 August 2021 · case 24/KPPU-I/2020 · PENGADAAN PAKET PEKERJAAN PEMBANGUNAN PELABUHAN JANGKAR KABUPATEN SITUBONDO TAHUN ANGGARAN 2018 · fine IDR 1,250,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 19 August 2021 · case 24/KPPU-I/2020 · PENGADAAN PAKET PEKERJAAN PEMBANGUNAN PELABUHAN JANGKAR KABUPATEN SITUBONDO TAHUN ANGGARAN 2018 · fine IDR 1,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 19 August 2021 · case 24/KPPU-I/2020 · PENGADAAN PAKET PEKERJAAN PEMBANGUNAN PELABUHAN JANGKAR KABUPATEN SITUBONDO TAHUN ANGGARAN 2018 · fine IDR 1,000,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 July 2021 · case 28/KPPU-I/2020 · PENGADAAN PAKET PEMBANGUNAN PELABUHAN PENYEBERANGAN PACIRAN KABUPATEN LAMONGAN TAHUN ANGGARAN 2018 · fine IDR 1,470,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 July 2021 · case 28/KPPU-I/2020 · PENGADAAN PAKET PEMBANGUNAN PELABUHAN PENYEBERANGAN PACIRAN KABUPATEN LAMONGAN TAHUN ANGGARAN 2018 · fine IDR 200,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 July 2021 · case 28/KPPU-I/2020 · PENGADAAN PAKET PEMBANGUNAN PELABUHAN PENYEBERANGAN PACIRAN KABUPATEN LAMONGAN TAHUN ANGGARAN 2018 · fine IDR 150,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 11 February 2021 · case 04/KPPU-L/2020 · TENDER PAKET PEKERJAAN PEMBANGUNAN RUMAH SAKIT RUJUKAN REGIONAL LANGSA SATKER DINAS KESEHATAN ACEH PEMERINTAH DAERAH PROVINSI ACEH TAHUN ANGGARAN 2018 (KODE LELANG: 17684106) · fine IDR 1,723,500,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 28 January 2021 · case 05/KPPU-I/2020 · LARANGAN PRAKTEK MONOPOLI DAN/ATAU PERSAINGAN USAHA TIDAK SEHAT (UNDANG-UNDANG NOMOR 5 TAHUN 1999) TERKAIT PENGADAAN PEKERJAAN PEMBANGUNAN GEDUNG KOLAM RENANG TAHAP II KECAMATAN KANDANGAN KABUPATEN HULU SUNGAI SELATAN TAHUN ANGGARAN 2017 · fine IDR 1,350,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 28 January 2021 · case 05/KPPU-I/2020 · LARANGAN PRAKTEK MONOPOLI DAN/ATAU PERSAINGAN USAHA TIDAK SEHAT (UNDANG-UNDANG NOMOR 5 TAHUN 1999) TERKAIT PENGADAAN PEKERJAAN PEMBANGUNAN GEDUNG KOLAM RENANG TAHAP II KECAMATAN KANDANGAN KABUPATEN HULU SUNGAI SELATAN TAHUN ANGGARAN 2017 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 28 January 2021 · case 05/KPPU-I/2020 · LARANGAN PRAKTEK MONOPOLI DAN/ATAU PERSAINGAN USAHA TIDAK SEHAT (UNDANG-UNDANG NOMOR 5 TAHUN 1999) TERKAIT PENGADAAN PEKERJAAN PEMBANGUNAN GEDUNG KOLAM RENANG TAHAP II KECAMATAN KANDANGAN KABUPATEN HULU SUNGAI SELATAN TAHUN ANGGARAN 2017 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 January 2021 · case 30/KPPU-I/2019 · TENDER PEMBANGUNAN JALAN RUAS NGAJAM – APULEA SEGMEN III (DESA NGAJAM – APULEA) PADA SATKER DINAS PEKERJAAN UMUM DAN PENATAAN RUANG PEMERINTAH DAERAH KABUPATEN HALMAHERA UTARA APBD TAHUN ANGGARAN 2018 - 2020 (KODE TENDER: 1455233) · fine IDR 1,100,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 January 2021 · case 30/KPPU-I/2019 · TENDER PEMBANGUNAN JALAN RUAS NGAJAM – APULEA SEGMEN III (DESA NGAJAM – APULEA) PADA SATKER DINAS PEKERJAAN UMUM DAN PENATAAN RUANG PEMERINTAH DAERAH KABUPATEN HALMAHERA UTARA APBD TAHUN ANGGARAN 2018 - 2020 (KODE TENDER: 1455233) · fine IDR 1,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 January 2021 · case 30/KPPU-I/2019 · TENDER PEMBANGUNAN JALAN RUAS NGAJAM – APULEA SEGMEN III (DESA NGAJAM – APULEA) PADA SATKER DINAS PEKERJAAN UMUM DAN PENATAAN RUANG PEMERINTAH DAERAH KABUPATEN HALMAHERA UTARA APBD TAHUN ANGGARAN 2018 - 2020 (KODE TENDER: 1455233) · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Rajawali Jaya Sakti Contrindo
Authority Indonesia Competition Commission (KPPU) · From 10 November 2020 · case 22/KPPU-I/2019 · PELELANGAN UMUM PAKET PEKERJAAN LANJUTAN PEMBANGUNAN JARINGAN DISTRIBUSI AIR BERSIH (MULTIYEARS) KABUPATEN PENAJAM PASER UTARA, KALIMANTAN TIMUR, APBD TAHUN ANGGARAN 2015-2018 (KODE LELANG 1684264) · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 10 November 2020 · case 22/KPPU-I/2019 · PELELANGAN UMUM PAKET PEKERJAAN LANJUTAN PEMBANGUNAN JARINGAN DISTRIBUSI AIR BERSIH (MULTIYEARS) KABUPATEN PENAJAM PASER UTARA, KALIMANTAN TIMUR, APBD TAHUN ANGGARAN 2015-2018 (KODE LELANG 1684264) · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Perusahaan Daerah Air Minum (PDAM) Way Rilau Kota Bandar Lampung
Authority Indonesia Competition Commission (KPPU) · From 26 February 2020 · case 14/KPPU-L/2019 · PELELANGAN PROYEK KERJA SAMA PEMERINTAH DENGAN BADAN USAHA TERKAIT SISTEM PENYEDIAAN AIR MINUM DI KOTA BANDAR LAMPUNG · fine IDR 1,747,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 26 February 2020 · case 14/KPPU-L/2019 · PELELANGAN PROYEK KERJA SAMA PEMERINTAH DENGAN BADAN USAHA TERKAIT SISTEM PENYEDIAAN AIR MINUM DI KOTA BANDAR LAMPUNG · fine IDR 3,843,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 26 February 2020 · case 14/KPPU-L/2019 · PELELANGAN PROYEK KERJA SAMA PEMERINTAH DENGAN BADAN USAHA TERKAIT SISTEM PENYEDIAAN AIR MINUM DI KOTA BANDAR LAMPUNG · fine IDR 2,358,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2019 · case 16/KPPU-I/2018 · PEKERJAAN PEMELIHARAAN BERKALA JALAN BATEBALLA-JATIA CS PADA SATUAN KERJA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN BANTAENG, APBD TAHUN ANGGARAN 2017 · fine IDR 4,066,900,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2019 · case 16/KPPU-I/2018 · PEKERJAAN PEMELIHARAAN BERKALA JALAN BATEBALLA-JATIA CS PADA SATUAN KERJA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN BANTAENG, APBD TAHUN ANGGARAN 2017 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2019 · case 16/KPPU-I/2018 · PEKERJAAN PEMELIHARAAN BERKALA JALAN BATEBALLA-JATIA CS PADA SATUAN KERJA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN BANTAENG, APBD TAHUN ANGGARAN 2017 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2019 · case 17/KPPU-I/2018 · TENDER PENINGKATAN JALAN KAMPUNG BAKARA-SABBANNYANG PADA SATUAN KERJA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN BANTAENG, APBD TAHUN ANGGARAN 2018 · fine IDR 2,963,200,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2019 · case 17/KPPU-I/2018 · TENDER PENINGKATAN JALAN KAMPUNG BAKARA-SABBANNYANG PADA SATUAN KERJA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN BANTAENG, APBD TAHUN ANGGARAN 2018 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2019 · case 17/KPPU-I/2018 · TENDER PENINGKATAN JALAN KAMPUNG BAKARA-SABBANNYANG PADA SATUAN KERJA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN BANTAENG, APBD TAHUN ANGGARAN 2018 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 11 September 2019 · case 21/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PENINGKATAN JALAN (KODE LELANG 583207) DAN PAKET PEKERJAAN PEMBANGUNAN JALAN (KODE LELANG 584207) PADA DINAS PEKERJAAN UMUM KABUPATEN KEDIRI SUMBER DANA DAU APBD KABUPATEN KEDIRI TA 2016 · fine IDR 6,746,894,000 · barred from tenders for 2 years · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 11 September 2019 · case 21/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PENINGKATAN JALAN (KODE LELANG 583207) DAN PAKET PEKERJAAN PEMBANGUNAN JALAN (KODE LELANG 584207) PADA DINAS PEKERJAAN UMUM KABUPATEN KEDIRI SUMBER DANA DAU APBD KABUPATEN KEDIRI TA 2016 · fine IDR 6,746,894,000 · barred from tenders for 2 years · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 11 September 2019 · case 21/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PENINGKATAN JALAN (KODE LELANG 583207) DAN PAKET PEKERJAAN PEMBANGUNAN JALAN (KODE LELANG 584207) PADA DINAS PEKERJAAN UMUM KABUPATEN KEDIRI SUMBER DANA DAU APBD KABUPATEN KEDIRI TA 2016 · fine IDR 1,927,684,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 11 September 2019 · case 21/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PENINGKATAN JALAN (KODE LELANG 583207) DAN PAKET PEKERJAAN PEMBANGUNAN JALAN (KODE LELANG 584207) PADA DINAS PEKERJAAN UMUM KABUPATEN KEDIRI SUMBER DANA DAU APBD KABUPATEN KEDIRI TA 2016 · fine IDR 1,927,684,000 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 11 September 2019 · case 21/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PENINGKATAN JALAN (KODE LELANG 583207) DAN PAKET PEKERJAAN PEMBANGUNAN JALAN (KODE LELANG 584207) PADA DINAS PEKERJAAN UMUM KABUPATEN KEDIRI SUMBER DANA DAU APBD KABUPATEN KEDIRI TA 2016 · fine IDR 1,760,059,000 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 11 September 2019 · case 22/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PENINGKATAN JALAN RIGID PAVEMENT RUAS WATES-PLOSOKLATEN (KODE LELANG 620207) PADA DINAS PEKERJAAN UMUM SUMBER DANA ALOKASI KHUSUS INFRASTRUKTUR PUBLIK DAERAH (DAK IPD) BIDANG JALAN TAHUN ANGGARAN 2016 · fine IDR 3,250,611,000 · barred from tenders for 2 years · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 11 September 2019 · case 22/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PENINGKATAN JALAN RIGID PAVEMENT RUAS WATES-PLOSOKLATEN (KODE LELANG 620207) PADA DINAS PEKERJAAN UMUM SUMBER DANA ALOKASI KHUSUS INFRASTRUKTUR PUBLIK DAERAH (DAK IPD) BIDANG JALAN TAHUN ANGGARAN 2016 · fine IDR 1,000,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 11 September 2019 · case 22/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PENINGKATAN JALAN RIGID PAVEMENT RUAS WATES-PLOSOKLATEN (KODE LELANG 620207) PADA DINAS PEKERJAAN UMUM SUMBER DANA ALOKASI KHUSUS INFRASTRUKTUR PUBLIK DAERAH (DAK IPD) BIDANG JALAN TAHUN ANGGARAN 2016 · fine IDR 1,000,000,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 11 September 2019 · case 22/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PENINGKATAN JALAN RIGID PAVEMENT RUAS WATES-PLOSOKLATEN (KODE LELANG 620207) PADA DINAS PEKERJAAN UMUM SUMBER DANA ALOKASI KHUSUS INFRASTRUKTUR PUBLIK DAERAH (DAK IPD) BIDANG JALAN TAHUN ANGGARAN 2016 · fine IDR 1,000,000,000 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 September 2019 · case 12/KPPU-I/2018 · PENINGKATAN JALAN DALAM KOTA TANA PASER (MULTIYEARS 2 TAHUN) PADA DINAS BINA MARGA, PENGAIRAN DAN TATA RUANG KABUPATEN PASER, KALIMANTAN TIMUR TAHUN ANGGARAN 2014-2015 · fine IDR 2,135,062,440 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 September 2019 · case 12/KPPU-I/2018 · PENINGKATAN JALAN DALAM KOTA TANA PASER (MULTIYEARS 2 TAHUN) PADA DINAS BINA MARGA, PENGAIRAN DAN TATA RUANG KABUPATEN PASER, KALIMANTAN TIMUR TAHUN ANGGARAN 2014-2015 · fine IDR 1,000,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 September 2019 · case 12/KPPU-I/2018 · PENINGKATAN JALAN DALAM KOTA TANA PASER (MULTIYEARS 2 TAHUN) PADA DINAS BINA MARGA, PENGAIRAN DAN TATA RUANG KABUPATEN PASER, KALIMANTAN TIMUR TAHUN ANGGARAN 2014-2015 · fine IDR 1,000,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 September 2019 · case 10/KPPU-I/2018 · PELELANGAN PEMBANGUNAN RUMAH SAKIT PADA SATUAN KERJA DINAS KESEHATAN KOTA MAKASSAR TAHUN ANGGARAN 2017-APBD · fine IDR 2,852,384,000 · barred from tenders for 2 years · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 September 2019 · case 10/KPPU-I/2018 · PELELANGAN PEMBANGUNAN RUMAH SAKIT PADA SATUAN KERJA DINAS KESEHATAN KOTA MAKASSAR TAHUN ANGGARAN 2017-APBD · fine IDR 1,901,589,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 September 2019 · case 10/KPPU-I/2018 · PELELANGAN PEMBANGUNAN RUMAH SAKIT PADA SATUAN KERJA DINAS KESEHATAN KOTA MAKASSAR TAHUN ANGGARAN 2017-APBD · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 August 2019 · case 18/KPPU-L/2018 · PEMBANGUNAN JALAN AKSES BANDARA SIBISA PADA SATUAN KERJA PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI SUMATERA UTARA APBN TAHUN ANGGARAN 2018 · fine IDR 1,253,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 August 2019 · case 18/KPPU-L/2018 · PEMBANGUNAN JALAN AKSES BANDARA SIBISA PADA SATUAN KERJA PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI SUMATERA UTARA APBN TAHUN ANGGARAN 2018 · fine IDR 1,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 23/KPPU-L/2018 · TENDER PRESERVASI DAN PELEBARAN JALAN BTS. PROVINSI ACEH - BARUS - SIBOLGA PADA SATKER PELAKSANAAN JALAN NASIONAL WILAYAH II PROVINSI SUMATERA UTARA APBN TAHUN ANGGARAN 2018 · fine IDR 1,260,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 23/KPPU-L/2018 · TENDER PRESERVASI DAN PELEBARAN JALAN BTS. PROVINSI ACEH - BARUS - SIBOLGA PADA SATKER PELAKSANAAN JALAN NASIONAL WILAYAH II PROVINSI SUMATERA UTARA APBN TAHUN ANGGARAN 2018 · fine IDR 1,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 23/KPPU-L/2018 · TENDER PRESERVASI DAN PELEBARAN JALAN BTS. PROVINSI ACEH - BARUS - SIBOLGA PADA SATKER PELAKSANAAN JALAN NASIONAL WILAYAH II PROVINSI SUMATERA UTARA APBN TAHUN ANGGARAN 2018 · fine IDR 1,000,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 14/KPPU-I/2018 · TENDER PAKET PRESERVASI REHABILITASI JALAN ZAENAL ARIFIN (STABAT) - BINJAI RAYA (MEDAN) - BELAWAN PADA SATUAN KERJA PELAKSANAAN JALAN NASIONAL METROPOLITAN MEDAN APBN TAHUN ANGGARAN 2017 · fine IDR 1,769,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 14/KPPU-I/2018 · TENDER PAKET PRESERVASI REHABILITASI JALAN ZAENAL ARIFIN (STABAT) - BINJAI RAYA (MEDAN) - BELAWAN PADA SATUAN KERJA PELAKSANAAN JALAN NASIONAL METROPOLITAN MEDAN APBN TAHUN ANGGARAN 2017 · fine IDR 1,769,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 19/KPPU-I/2018 · PAKET PEKERJAAN PEMBANGUNAN JALAN (KODE LELANG 770207) DAN PAKET PENINGKATAN JALAN (KODE LELANG 771207) OLEH DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN KEDIRI SUMBER DANA DAU APBD KABUPATEN KEDIRI TA 2017 · fine IDR 582,600,000,000 · barred from tenders for 2 years (Indonesia) · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 19/KPPU-I/2018 · PAKET PEKERJAAN PEMBANGUNAN JALAN (KODE LELANG 770207) DAN PAKET PENINGKATAN JALAN (KODE LELANG 771207) OLEH DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN KEDIRI SUMBER DANA DAU APBD KABUPATEN KEDIRI TA 2017 · fine IDR 582,600,000,000 · barred from tenders for 2 years (Indonesia) · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 19/KPPU-I/2018 · PAKET PEKERJAAN PEMBANGUNAN JALAN (KODE LELANG 770207) DAN PAKET PENINGKATAN JALAN (KODE LELANG 771207) OLEH DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN KEDIRI SUMBER DANA DAU APBD KABUPATEN KEDIRI TA 2017 · fine IDR 194,200,000,000 · barred from tenders for 1 year (Indonesia) · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 19/KPPU-I/2018 · PAKET PEKERJAAN PEMBANGUNAN JALAN (KODE LELANG 770207) DAN PAKET PENINGKATAN JALAN (KODE LELANG 771207) OLEH DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN KEDIRI SUMBER DANA DAU APBD KABUPATEN KEDIRI TA 2017 · fine IDR 194,200,000,000 · barred from tenders for 1 year (Indonesia) · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 20/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PEMELIHARAAN BERKALA JALAN (KODE LELANG 902207) PADA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG (PUPR) SUMBER DANA SPESIFIC GRANT/APBD KABUPATEN KEDIRI TA 2017 · fine IDR 3,700,000,000 · barred from tenders for 2 years (Indonesia) · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 20/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PEMELIHARAAN BERKALA JALAN (KODE LELANG 902207) PADA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG (PUPR) SUMBER DANA SPESIFIC GRANT/APBD KABUPATEN KEDIRI TA 2017 · fine IDR 1,000,000,000 · barred from tenders for 1 year (Indonesia) · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 20/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PEMELIHARAAN BERKALA JALAN (KODE LELANG 902207) PADA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG (PUPR) SUMBER DANA SPESIFIC GRANT/APBD KABUPATEN KEDIRI TA 2017 · fine IDR 1,000,000,000 · barred from tenders for 1 year (Indonesia) · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2019 · case 20/KPPU-I/2018 · PELELANGAN PAKET PEKERJAAN PEMELIHARAAN BERKALA JALAN (KODE LELANG 902207) PADA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG (PUPR) SUMBER DANA SPESIFIC GRANT/APBD KABUPATEN KEDIRI TA 2017 · barred from tenders for 1 year (Indonesia) · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 August 2019 · case 13/KPPU-L/2018 · PAKET PEMBANGUNAN JALAN BALIGE BY PASS PADA SATKER PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI SUMATERA UTARA TAHUN ANGGARAN 2017 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 August 2019 · case 13/KPPU-L/2018 · PAKET PEMBANGUNAN JALAN BALIGE BY PASS PADA SATKER PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI SUMATERA UTARA TAHUN ANGGARAN 2017 · barred from tenders for 1 year (Indonesia) · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Anugrah Bahari Sejahtera Mandiri
Authority Indonesia Competition Commission (KPPU) · From 20 August 2019 · case 13/KPPU-L/2018 · PAKET PEMBANGUNAN JALAN BALIGE BY PASS PADA SATKER PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI SUMATERA UTARA TAHUN ANGGARAN 2017 · barred from tenders for 3 years (Indonesia) · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 9 April 2019 · case 04/KPPU-L/2018 · LELANG PRESERVASI REKONSTRUKSI JALAN DAN PEMELIHARAAN RUTIN JEMBATAN PALANGKA RAYA-BAGUGUS-BUKIT BATU, KALIMANTAN TENGAH, SATKER PELAKSANAAN JALAN NASIONAL WILAYAH III, TAHUN ANGGARAN 2017 · fine IDR 1,709,446,598 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 9 April 2019 · case 04/KPPU-L/2018 · LELANG PRESERVASI REKONSTRUKSI JALAN DAN PEMELIHARAAN RUTIN JEMBATAN PALANGKA RAYA-BAGUGUS-BUKIT BATU, KALIMANTAN TENGAH, SATKER PELAKSANAAN JALAN NASIONAL WILAYAH III, TAHUN ANGGARAN 2017 · fine IDR 1,000,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Mellindo Bhakti Persadatama
Authority Indonesia Competition Commission (KPPU) · From 9 April 2019 · case 05/KPPU-L/2018 · LELANG PRESERVASI REKONSTRUKSI JALAN DAN PEMELIHARAAN RUTIN JEMBATAN BUKIT BATU - LUNGKUH LAYANG - KALAHIEN, SATUAN KERJA PELAKSANAAN JALAN NASIONAL WILAYAH III, PROVINSI KALIMANTAN TENGAH, TAHUN ANGGARAN 2017 · fine IDR 1,034,999,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 9 April 2019 · case 05/KPPU-L/2018 · LELANG PRESERVASI REKONSTRUKSI JALAN DAN PEMELIHARAAN RUTIN JEMBATAN BUKIT BATU - LUNGKUH LAYANG - KALAHIEN, SATUAN KERJA PELAKSANAAN JALAN NASIONAL WILAYAH III, PROVINSI KALIMANTAN TENGAH, TAHUN ANGGARAN 2017 · fine IDR 1,086,749,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Mellindo Bhakti Persadatama
Authority Indonesia Competition Commission (KPPU) · From 9 April 2019 · case 06/KPPU-L/2018 · PAKET LELANG PRESERVASI REKONSTRUKSI JALAN DAN PEMELIHARAAN RUTIN JEMBATAN KALAHIEN - BUNTOK - AMPAH DI LINGKUNGAN POKJA SATKER PELAKSANA JALAN NASIONAL WILAYAH III PROVINSI KALIMANTAN TENGAH TAHUN ANGGARAN 2017 · fine IDR 1,152,144,270 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 9 April 2019 · case 06/KPPU-L/2018 · PAKET LELANG PRESERVASI REKONSTRUKSI JALAN DAN PEMELIHARAAN RUTIN JEMBATAN KALAHIEN - BUNTOK - AMPAH DI LINGKUNGAN POKJA SATKER PELAKSANA JALAN NASIONAL WILAYAH III PROVINSI KALIMANTAN TENGAH TAHUN ANGGARAN 2017 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 9 April 2019 · case 06/KPPU-L/2018 · PAKET LELANG PRESERVASI REKONSTRUKSI JALAN DAN PEMELIHARAAN RUTIN JEMBATAN KALAHIEN - BUNTOK - AMPAH DI LINGKUNGAN POKJA SATKER PELAKSANA JALAN NASIONAL WILAYAH III PROVINSI KALIMANTAN TENGAH TAHUN ANGGARAN 2017 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 February 2019 · case 11/KPPU-I/2017 · PRESERVASI REKONSTRUKSI ESANG-RAINIS-MELONGUANE-BEO PADA SATUAN KERJA PELAKSANA JALAN NASIONAL WILAYAH III SULAWESI UTARA (SANGIHE TALAUD) TAHUN ANGGARAN 2017 · fine IDR 3,665,873,880 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 February 2019 · case 11/KPPU-I/2017 · PRESERVASI REKONSTRUKSI ESANG-RAINIS-MELONGUANE-BEO PADA SATUAN KERJA PELAKSANA JALAN NASIONAL WILAYAH III SULAWESI UTARA (SANGIHE TALAUD) TAHUN ANGGARAN 2017 · fine IDR 1,000,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Mellindo Bhakti Persadatama
Authority Indonesia Competition Commission (KPPU) · From 10 January 2019 · case 03/KPPU-L/2018 · TENDER PAKET PRESERVASI REKONSTRUKSI JALAN DAN PEMELIHARAAN RUTIN JEMBATAN SIMPANG SEI ASAM - TARAKAS - TUMBANG TALAKEN PADA SATUAN TUGAS KERJA DINAS PEKERJAAN UMUM PROVINSI KALIMANTAN TENGAH TAHUN ANGGARAN 2017 · fine IDR 1,565,000,000 · barred from tenders for 2 years (Indonesia) · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 10 January 2019 · case 03/KPPU-L/2018 · TENDER PAKET PRESERVASI REKONSTRUKSI JALAN DAN PEMELIHARAAN RUTIN JEMBATAN SIMPANG SEI ASAM - TARAKAS - TUMBANG TALAKEN PADA SATUAN TUGAS KERJA DINAS PEKERJAAN UMUM PROVINSI KALIMANTAN TENGAH TAHUN ANGGARAN 2017 · fine IDR 1,000,000,000 · barred from tenders for 2 years (Indonesia) · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 10 January 2019 · case 03/KPPU-L/2018 · TENDER PAKET PRESERVASI REKONSTRUKSI JALAN DAN PEMELIHARAAN RUTIN JEMBATAN SIMPANG SEI ASAM - TARAKAS - TUMBANG TALAKEN PADA SATUAN TUGAS KERJA DINAS PEKERJAAN UMUM PROVINSI KALIMANTAN TENGAH TAHUN ANGGARAN 2017 · fine IDR 1,000,000,000 · barred from tenders for 1 year (Indonesia) · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 December 2018 · case 10/KPPU-I/2017 · PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN STADION MANDALA KRIDA APBD TAHUN ANGGARAN 2016 DAN PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN STADION MANDALA KRIDA APBDP TAHUN ANGGARAN 2017 PROVINSI DAERAH ISTIMEWA YOGYAKARTA · fine IDR 2,509,000,000 · barred from tenders for 2 years (Indonesia) · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 December 2018 · case 10/KPPU-I/2017 · PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN STADION MANDALA KRIDA APBD TAHUN ANGGARAN 2016 DAN PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN STADION MANDALA KRIDA APBDP TAHUN ANGGARAN 2017 PROVINSI DAERAH ISTIMEWA YOGYAKARTA · fine IDR 1,000,000,000 · respondent IX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 December 2018 · case 10/KPPU-I/2017 · PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN STADION MANDALA KRIDA APBD TAHUN ANGGARAN 2016 DAN PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN STADION MANDALA KRIDA APBDP TAHUN ANGGARAN 2017 PROVINSI DAERAH ISTIMEWA YOGYAKARTA · fine IDR 1,000,000,000 · barred from tenders for 1 year (Indonesia) · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 December 2018 · case 10/KPPU-I/2017 · PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN STADION MANDALA KRIDA APBD TAHUN ANGGARAN 2016 DAN PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN STADION MANDALA KRIDA APBDP TAHUN ANGGARAN 2017 PROVINSI DAERAH ISTIMEWA YOGYAKARTA · fine IDR 1,000,000,000 · barred from tenders for 1 year (Indonesia) · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 December 2018 · case 10/KPPU-I/2017 · PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN STADION MANDALA KRIDA APBD TAHUN ANGGARAN 2016 DAN PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN STADION MANDALA KRIDA APBDP TAHUN ANGGARAN 2017 PROVINSI DAERAH ISTIMEWA YOGYAKARTA · fine IDR 1,070,000,000 · barred from tenders for 1 year (Indonesia) · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 December 2018 · case 10/KPPU-I/2017 · PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN STADION MANDALA KRIDA APBD TAHUN ANGGARAN 2016 DAN PENGADAAN PEKERJAAN KONSTRUKSI PEMBANGUNAN STADION MANDALA KRIDA APBDP TAHUN ANGGARAN 2017 PROVINSI DAERAH ISTIMEWA YOGYAKARTA · fine IDR 1,322,000,000 · barred from tenders for 2 years (Indonesia) · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 11 October 2018 · case 04/KPPU-L/2017 · TENDER PROVISION OF UNDER WATER SERVICES FOR KEPODANG AND KETAPANG FIELD (TENDER NO. 11204) · fine IDR 1,243,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 11 October 2018 · case 04/KPPU-L/2017 · TENDER PROVISION OF UNDER WATER SERVICES FOR KEPODANG AND KETAPANG FIELD (TENDER NO. 11204) · fine IDR 1,243,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Aquamarine Divindo Inspection
Authority Indonesia Competition Commission (KPPU) · From 11 October 2018 · case 04/KPPU-L/2017 · TENDER PROVISION OF UNDER WATER SERVICES FOR KEPODANG AND KETAPANG FIELD (TENDER NO. 11204) · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 September 2018 · case 01/KPPU-L/2017 · TENDER PAKET PEKERJAANPENINGKATAN KAPASITAS/PELEBARAN JALAN KABANJAHE-KUTABULUH TAHUN ANGGARAN 2013-2014 (MULTIYEARS) DAN PAKET TENDER PEKERJAAN PELEBARAN JALAN BTS. KABANJAHE-KUTABULU TAHUN 2015 PADA SATUAN KERJA PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI SUMATERA UTARA · fine IDR 1,518,600,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Multhi Bangun Cipta Persada
Authority Indonesia Competition Commission (KPPU) · From 4 September 2018 · case 01/KPPU-L/2017 · TENDER PAKET PEKERJAANPENINGKATAN KAPASITAS/PELEBARAN JALAN KABANJAHE-KUTABULUH TAHUN ANGGARAN 2013-2014 (MULTIYEARS) DAN PAKET TENDER PEKERJAAN PELEBARAN JALAN BTS. KABANJAHE-KUTABULU TAHUN 2015 PADA SATUAN KERJA PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI SUMATERA UTARA · fine IDR 1,712,700,000 · barred from tenders for 2 years (Indonesia) · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 September 2018 · case 01/KPPU-L/2017 · TENDER PAKET PEKERJAANPENINGKATAN KAPASITAS/PELEBARAN JALAN KABANJAHE-KUTABULUH TAHUN ANGGARAN 2013-2014 (MULTIYEARS) DAN PAKET TENDER PEKERJAAN PELEBARAN JALAN BTS. KABANJAHE-KUTABULU TAHUN 2015 PADA SATUAN KERJA PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI SUMATERA UTARA · fine IDR 1,106,600,000 · barred from tenders for 2 years (Indonesia) · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 January 2018 · case 21/KPPU-I/2016 · DUGAAN PELANGGARAN PASAL 22 UNDANG - UNDANG NOMOR 5 TAHUN 1999 TERKAIT PAKET PEKERJAAN PENINGKATAN JALAN LUBUK JAMBI-SP.IBUL-SP.IFA DI KABUPATEN KUANTAN SINGINGI-PROVINSI RIAU PADA DINAS BINA MARGA PROVINSI RIAU TAHUN ANGGARAN 2015 · fine IDR 2,062,800,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 January 2018 · case 21/KPPU-I/2016 · DUGAAN PELANGGARAN PASAL 22 UNDANG - UNDANG NOMOR 5 TAHUN 1999 TERKAIT PAKET PEKERJAAN PENINGKATAN JALAN LUBUK JAMBI-SP.IBUL-SP.IFA DI KABUPATEN KUANTAN SINGINGI-PROVINSI RIAU PADA DINAS BINA MARGA PROVINSI RIAU TAHUN ANGGARAN 2015 · fine IDR 515,700,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 14 November 2017 · case 18/KPPU-I/2016 · PAKET PEKERJAAN PRESERVASI DAN PELEBARAN BTS. PROVINSI RIAU-MERLUNG-SP. NIAM APBN TAHUN ANGGARAN 2016 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 14 November 2017 · case 18/KPPU-I/2016 · PAKET PEKERJAAN PRESERVASI DAN PELEBARAN BTS. PROVINSI RIAU-MERLUNG-SP. NIAM APBN TAHUN ANGGARAN 2016 · fine IDR 588,400,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 14 November 2017 · case 18/KPPU-I/2016 · PAKET PEKERJAAN PRESERVASI DAN PELEBARAN BTS. PROVINSI RIAU-MERLUNG-SP. NIAM APBN TAHUN ANGGARAN 2016 · fine IDR 588,400,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 14 November 2017 · case 19/KPPU-I/2016 · PAKET PEKERJAAN PRESERVASI DAN PELEBARAN JALAN ARAH MUARA TEBO/PATTIMURA (MUARA BUNGO) – SEI. BENGKAL · fine IDR 1,957,486,847 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 14 November 2017 · case 19/KPPU-I/2016 · PAKET PEKERJAAN PRESERVASI DAN PELEBARAN JALAN ARAH MUARA TEBO/PATTIMURA (MUARA BUNGO) – SEI. BENGKAL · fine IDR 978,743,424 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 14 November 2017 · case 19/KPPU-I/2016 · PAKET PEKERJAAN PRESERVASI DAN PELEBARAN JALAN ARAH MUARA TEBO/PATTIMURA (MUARA BUNGO) – SEI. BENGKAL · fine IDR 978,743,424 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 October 2017 · case 16/KPPU-I/2016 · BERKAITAN DENGAN PAKET PENGADAAN PEMBANGUNAN SARANA DAN PRASARANA PENDIDIKAN UNIT PELAKSANA TEKNIS DAERAH (UPTD) SEKOLAH KHUSUS OLAHRAGAWAN INTERNASIONAL (SKOI) PROVINSI KALIMANTAN TIMUR, TAHUN ANGGARAN 2013 · fine IDR 444,175,200 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 October 2017 · case 16/KPPU-I/2016 · BERKAITAN DENGAN PAKET PENGADAAN PEMBANGUNAN SARANA DAN PRASARANA PENDIDIKAN UNIT PELAKSANA TEKNIS DAERAH (UPTD) SEKOLAH KHUSUS OLAHRAGAWAN INTERNASIONAL (SKOI) PROVINSI KALIMANTAN TIMUR, TAHUN ANGGARAN 2013 · fine IDR 190,360,800 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2017 · case 17/KPPU-I/2016 · PENINGKATAN JALAN JONGKANG MENUJU JALAN JAKARTA SAMARINDA KARANG PACI (RING ROAD III) KECAMATAN TENGGARONG SEBERANG · fine IDR 502,102,800,000 · barred from tenders for 2 years (Indonesia) · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 August 2017 · case 17/KPPU-I/2016 · PENINGKATAN JALAN JONGKANG MENUJU JALAN JAKARTA SAMARINDA KARANG PACI (RING ROAD III) KECAMATAN TENGGARONG SEBERANG · fine IDR 502,102,800,000 · barred from tenders for 2 years (Indonesia) · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 August 2017 · case 14/KPPU-L/2016 · PEMBANGUNAN (PENGEMBANGAN) FASILITAS PELABUHAN LAUT BENTENG KABUPATEN SELAYAR APBN TAHUN ANGGARAN 2015 DAN PEMBANGUNAN PENGEMBANGAN) FASILITAS PELABUHAN LAUT BENTENG KABUPATEN SELAYAR APBN-P TAHUN ANGGARAN 2015 · fine IDR 1,842,659,000 · barred from tenders for 2 years · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 August 2017 · case 14/KPPU-L/2016 · PEMBANGUNAN (PENGEMBANGAN) FASILITAS PELABUHAN LAUT BENTENG KABUPATEN SELAYAR APBN TAHUN ANGGARAN 2015 DAN PEMBANGUNAN PENGEMBANGAN) FASILITAS PELABUHAN LAUT BENTENG KABUPATEN SELAYAR APBN-P TAHUN ANGGARAN 2015 · fine IDR 1,000,000,000 · barred from tenders for 2 years · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 August 2017 · case 14/KPPU-L/2016 · PEMBANGUNAN (PENGEMBANGAN) FASILITAS PELABUHAN LAUT BENTENG KABUPATEN SELAYAR APBN TAHUN ANGGARAN 2015 DAN PEMBANGUNAN PENGEMBANGAN) FASILITAS PELABUHAN LAUT BENTENG KABUPATEN SELAYAR APBN-P TAHUN ANGGARAN 2015 · fine IDR 1,000,000,000 · barred from tenders for 2 years · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 August 2017 · case 15/KPPU-I/2016 · PAKET PELELANGAN PROYEK PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA, PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA-BTS.KALTIM, PROYEK PELEBARAN JALAN NANGA SEMANGUT-BTS.KOTA PUTUSSIBAU-TANJUNG KERJA DAN PROYEK PELEBARAN JALAN NANGA SEMANGUT-PUTUSSIBAU KALIMANTAN BARAT · fine IDR 4,084,800,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 August 2017 · case 15/KPPU-I/2016 · PAKET PELELANGAN PROYEK PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA, PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA-BTS.KALTIM, PROYEK PELEBARAN JALAN NANGA SEMANGUT-BTS.KOTA PUTUSSIBAU-TANJUNG KERJA DAN PROYEK PELEBARAN JALAN NANGA SEMANGUT-PUTUSSIBAU KALIMANTAN BARAT · fine IDR 2,245,800,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 August 2017 · case 15/KPPU-I/2016 · PAKET PELELANGAN PROYEK PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA, PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA-BTS.KALTIM, PROYEK PELEBARAN JALAN NANGA SEMANGUT-BTS.KOTA PUTUSSIBAU-TANJUNG KERJA DAN PROYEK PELEBARAN JALAN NANGA SEMANGUT-PUTUSSIBAU KALIMANTAN BARAT · fine IDR 1,223,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 August 2017 · case 15/KPPU-I/2016 · PAKET PELELANGAN PROYEK PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA, PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA-BTS.KALTIM, PROYEK PELEBARAN JALAN NANGA SEMANGUT-BTS.KOTA PUTUSSIBAU-TANJUNG KERJA DAN PROYEK PELEBARAN JALAN NANGA SEMANGUT-PUTUSSIBAU KALIMANTAN BARAT · fine IDR 116,400,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 August 2017 · case 15/KPPU-I/2016 · PAKET PELELANGAN PROYEK PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA, PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA-BTS.KALTIM, PROYEK PELEBARAN JALAN NANGA SEMANGUT-BTS.KOTA PUTUSSIBAU-TANJUNG KERJA DAN PROYEK PELEBARAN JALAN NANGA SEMANGUT-PUTUSSIBAU KALIMANTAN BARAT · fine IDR 91,900,000 · respondent IX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 August 2017 · case 15/KPPU-I/2016 · PAKET PELELANGAN PROYEK PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA, PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA-BTS.KALTIM, PROYEK PELEBARAN JALAN NANGA SEMANGUT-BTS.KOTA PUTUSSIBAU-TANJUNG KERJA DAN PROYEK PELEBARAN JALAN NANGA SEMANGUT-PUTUSSIBAU KALIMANTAN BARAT · fine IDR 110,600,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 August 2017 · case 15/KPPU-I/2016 · PAKET PELELANGAN PROYEK PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA, PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA-BTS.KALTIM, PROYEK PELEBARAN JALAN NANGA SEMANGUT-BTS.KOTA PUTUSSIBAU-TANJUNG KERJA DAN PROYEK PELEBARAN JALAN NANGA SEMANGUT-PUTUSSIBAU KALIMANTAN BARAT · fine IDR 202,500,000 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 August 2017 · case 15/KPPU-I/2016 · PAKET PELELANGAN PROYEK PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA, PENINGKATAN STRUKTUR JALAN PUTUSSIBAU-NANGA ERA-BTS.KALTIM, PROYEK PELEBARAN JALAN NANGA SEMANGUT-BTS.KOTA PUTUSSIBAU-TANJUNG KERJA DAN PROYEK PELEBARAN JALAN NANGA SEMANGUT-PUTUSSIBAU KALIMANTAN BARAT · fine IDR 2,071,800,000 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 July 2017 · case 24/KPPU-I/2016 · 4 (EMPAT) PAKET PENGADAAN ALAT KEDOKTERAN DI RSUD ABDUL WAHAB SJAHRANIE SAMARINDA, KALIMANTAN TIMUR TAHUN ANGGARAN 2012 DAN 2013 · fine IDR 2,050,400,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 July 2017 · case 24/KPPU-I/2016 · 4 (EMPAT) PAKET PENGADAAN ALAT KEDOKTERAN DI RSUD ABDUL WAHAB SJAHRANIE SAMARINDA, KALIMANTAN TIMUR TAHUN ANGGARAN 2012 DAN 2013 · fine IDR 233,300,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 July 2017 · case 24/KPPU-I/2016 · 4 (EMPAT) PAKET PENGADAAN ALAT KEDOKTERAN DI RSUD ABDUL WAHAB SJAHRANIE SAMARINDA, KALIMANTAN TIMUR TAHUN ANGGARAN 2012 DAN 2013 · fine IDR 275,100,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 July 2017 · case 24/KPPU-I/2016 · 4 (EMPAT) PAKET PENGADAAN ALAT KEDOKTERAN DI RSUD ABDUL WAHAB SJAHRANIE SAMARINDA, KALIMANTAN TIMUR TAHUN ANGGARAN 2012 DAN 2013 · fine IDR 41,800,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 July 2017 · case 24/KPPU-I/2016 · 4 (EMPAT) PAKET PENGADAAN ALAT KEDOKTERAN DI RSUD ABDUL WAHAB SJAHRANIE SAMARINDA, KALIMANTAN TIMUR TAHUN ANGGARAN 2012 DAN 2013 · fine IDR 152,100,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 March 2017 · case 06/KPPU-L/2016 · PAKET PEKERJAAN PEMBANGUNAN BENDUNG DI SIDILANITANO 2420 HA KABUPATEN TAPANULI UTARA DAN PAKET PEKERJAAN BENDUNG DI SITAKKURAK 1000 HA KABUPATEN TAPANULI TENGAH TAHUN ANGGARAN 2015-2017 (MULTIYEARS) · fine IDR 3,335,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 March 2017 · case 06/KPPU-L/2016 · PAKET PEKERJAAN PEMBANGUNAN BENDUNG DI SIDILANITANO 2420 HA KABUPATEN TAPANULI UTARA DAN PAKET PEKERJAAN BENDUNG DI SITAKKURAK 1000 HA KABUPATEN TAPANULI TENGAH TAHUN ANGGARAN 2015-2017 (MULTIYEARS) · fine IDR 4,711,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 March 2017 · case 06/KPPU-L/2016 · PAKET PEKERJAAN PEMBANGUNAN BENDUNG DI SIDILANITANO 2420 HA KABUPATEN TAPANULI UTARA DAN PAKET PEKERJAAN BENDUNG DI SITAKKURAK 1000 HA KABUPATEN TAPANULI TENGAH TAHUN ANGGARAN 2015-2017 (MULTIYEARS) · fine IDR 893,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 27 February 2017 · case 05/KPPU-L/2016 · 4 (EMPAT) PAKET PEMBORONGAN PEKERJAAN PELAYANAN TEKNIK PADA PLN (PERSERO) AREA RANTAU PRAPAT TAHUN 2015-2020 · fine IDR 1,239,204,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 27 February 2017 · case 05/KPPU-L/2016 · 4 (EMPAT) PAKET PEMBORONGAN PEKERJAAN PELAYANAN TEKNIK PADA PLN (PERSERO) AREA RANTAU PRAPAT TAHUN 2015-2020 · fine IDR 1,239,204,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 February 2017 · case 07/KPPU-L/2016 · PENGADAAN PUPUK INTENSIFIKASI TANAMAN KAKAO DI DINAS PERKEBUNAN PROVINSI SULAWESI SELATAN TAHUN ANGGARAN 2015 · fine IDR 1,939,355,520 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 February 2017 · case 07/KPPU-L/2016 · PENGADAAN PUPUK INTENSIFIKASI TANAMAN KAKAO DI DINAS PERKEBUNAN PROVINSI SULAWESI SELATAN TAHUN ANGGARAN 2015 · fine IDR 645,227,520 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 February 2017 · case 07/KPPU-L/2016 · PENGADAAN PUPUK INTENSIFIKASI TANAMAN KAKAO DI DINAS PERKEBUNAN PROVINSI SULAWESI SELATAN TAHUN ANGGARAN 2015 · fine IDR 646,177,920 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 February 2017 · case 07/KPPU-L/2016 · PENGADAAN PUPUK INTENSIFIKASI TANAMAN KAKAO DI DINAS PERKEBUNAN PROVINSI SULAWESI SELATAN TAHUN ANGGARAN 2015 · fine IDR 651,563,520 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 February 2017 · case 07/KPPU-L/2016 · PENGADAAN PUPUK INTENSIFIKASI TANAMAN KAKAO DI DINAS PERKEBUNAN PROVINSI SULAWESI SELATAN TAHUN ANGGARAN 2015 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 February 2017 · case 07/KPPU-L/2016 · PENGADAAN PUPUK INTENSIFIKASI TANAMAN KAKAO DI DINAS PERKEBUNAN PROVINSI SULAWESI SELATAN TAHUN ANGGARAN 2015 · fine IDR 2,590,379,520 · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 25 October 2016 · case 03/KPPU-L/2016 · TENDER/LELANG JACK-UP DRILLING RIG SERVICES FOR BD (NOMOR: PT 2140720/PT 2140720R) · fine IDR 11,600,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 25 October 2016 · case 03/KPPU-L/2016 · TENDER/LELANG JACK-UP DRILLING RIG SERVICES FOR BD (NOMOR: PT 2140720/PT 2140720R) · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 October 2016 · case 18/KPPU-L/2015 · PROSES PELELANGAN PEKERJAAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (CARPORT DAN GEDUNG BAGIAN UTARA) DAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (GEDUNG AULA DAN GEDUNG BAGIAN SELATAN) TAHUN ANGGARAN 2013 SERTA PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN UTARA KANTOR BUPATI LABUHANBATU SELATAN (TAHAP II) DAN PEKERJAAN PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN SELATAN · fine IDR 2,133,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 October 2016 · case 18/KPPU-L/2015 · PROSES PELELANGAN PEKERJAAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (CARPORT DAN GEDUNG BAGIAN UTARA) DAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (GEDUNG AULA DAN GEDUNG BAGIAN SELATAN) TAHUN ANGGARAN 2013 SERTA PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN UTARA KANTOR BUPATI LABUHANBATU SELATAN (TAHAP II) DAN PEKERJAAN PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN SELATAN · fine IDR 511,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 October 2016 · case 18/KPPU-L/2015 · PROSES PELELANGAN PEKERJAAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (CARPORT DAN GEDUNG BAGIAN UTARA) DAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (GEDUNG AULA DAN GEDUNG BAGIAN SELATAN) TAHUN ANGGARAN 2013 SERTA PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN UTARA KANTOR BUPATI LABUHANBATU SELATAN (TAHAP II) DAN PEKERJAAN PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN SELATAN · fine IDR 761,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 October 2016 · case 18/KPPU-L/2015 · PROSES PELELANGAN PEKERJAAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (CARPORT DAN GEDUNG BAGIAN UTARA) DAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (GEDUNG AULA DAN GEDUNG BAGIAN SELATAN) TAHUN ANGGARAN 2013 SERTA PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN UTARA KANTOR BUPATI LABUHANBATU SELATAN (TAHAP II) DAN PEKERJAAN PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN SELATAN · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 October 2016 · case 18/KPPU-L/2015 · PROSES PELELANGAN PEKERJAAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (CARPORT DAN GEDUNG BAGIAN UTARA) DAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (GEDUNG AULA DAN GEDUNG BAGIAN SELATAN) TAHUN ANGGARAN 2013 SERTA PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN UTARA KANTOR BUPATI LABUHANBATU SELATAN (TAHAP II) DAN PEKERJAAN PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN SELATAN · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 October 2016 · case 18/KPPU-L/2015 · PROSES PELELANGAN PEKERJAAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (CARPORT DAN GEDUNG BAGIAN UTARA) DAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (GEDUNG AULA DAN GEDUNG BAGIAN SELATAN) TAHUN ANGGARAN 2013 SERTA PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN UTARA KANTOR BUPATI LABUHANBATU SELATAN (TAHAP II) DAN PEKERJAAN PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN SELATAN · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 October 2016 · case 18/KPPU-L/2015 · PROSES PELELANGAN PEKERJAAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (CARPORT DAN GEDUNG BAGIAN UTARA) DAN LANJUTAN PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR BUPATI LABUHANBATU SELATAN (GEDUNG AULA DAN GEDUNG BAGIAN SELATAN) TAHUN ANGGARAN 2013 SERTA PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN UTARA KANTOR BUPATI LABUHANBATU SELATAN (TAHAP II) DAN PEKERJAAN PEMBANGUNAN KONSTRUKSI GEDUNG BAGIAN SELATAN · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2016 · case 22/KPPU-I/2015 · PELELANGAN PEMBANGUNAN PELABUHAN PERIKANAN GUGOP-LAMPUYANG (LANJUTAN) PADA SATKER BADAN PENGUSAHAAN KAWASAN PERDAGANGAN BEBAS DAN PELABUHAN BEBAS (BPKS) SABANG TAHUN ANGGARAN 2014 · fine IDR 1,105,616,000 · barred from tenders for 2 years · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2016 · case 22/KPPU-I/2015 · PELELANGAN PEMBANGUNAN PELABUHAN PERIKANAN GUGOP-LAMPUYANG (LANJUTAN) PADA SATKER BADAN PENGUSAHAAN KAWASAN PERDAGANGAN BEBAS DAN PELABUHAN BEBAS (BPKS) SABANG TAHUN ANGGARAN 2014 · fine IDR 1,005,105,000 · barred from tenders for 2 years · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2016 · case 22/KPPU-I/2015 · PELELANGAN PEMBANGUNAN PELABUHAN PERIKANAN GUGOP-LAMPUYANG (LANJUTAN) PADA SATKER BADAN PENGUSAHAAN KAWASAN PERDAGANGAN BEBAS DAN PELABUHAN BEBAS (BPKS) SABANG TAHUN ANGGARAN 2014 · fine IDR 804,084,000 · barred from tenders for 2 years · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2016 · case 22/KPPU-I/2015 · PELELANGAN PEMBANGUNAN PELABUHAN PERIKANAN GUGOP-LAMPUYANG (LANJUTAN) PADA SATKER BADAN PENGUSAHAAN KAWASAN PERDAGANGAN BEBAS DAN PELABUHAN BEBAS (BPKS) SABANG TAHUN ANGGARAN 2014 · barred from tenders for 2 years · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2016 · case 22/KPPU-I/2015 · PELELANGAN PEMBANGUNAN PELABUHAN PERIKANAN GUGOP-LAMPUYANG (LANJUTAN) PADA SATKER BADAN PENGUSAHAAN KAWASAN PERDAGANGAN BEBAS DAN PELABUHAN BEBAS (BPKS) SABANG TAHUN ANGGARAN 2014 · barred from tenders for 2 years · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 September 2016 · case 19/KPPU-I/2015 · PELELANGAN REHABILITASI/PEMELIHARAAN JALAN (APBD II) OLEH SATUAN KERJA DINAS PEKERJAAN UMUM KOTA MAKASSAR TAHUN ANGGARAN 2014 · fine IDR 1,472,514,000 · barred from tenders for 2 years · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 September 2016 · case 19/KPPU-I/2015 · PELELANGAN REHABILITASI/PEMELIHARAAN JALAN (APBD II) OLEH SATUAN KERJA DINAS PEKERJAAN UMUM KOTA MAKASSAR TAHUN ANGGARAN 2014 · fine IDR 1,099,812,000 · barred from tenders for 2 years · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 September 2016 · case 19/KPPU-I/2015 · PELELANGAN REHABILITASI/PEMELIHARAAN JALAN (APBD II) OLEH SATUAN KERJA DINAS PEKERJAAN UMUM KOTA MAKASSAR TAHUN ANGGARAN 2014 · fine IDR 426,602,000 · barred from tenders for 2 years · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 September 2016 · case 19/KPPU-I/2015 · PELELANGAN REHABILITASI/PEMELIHARAAN JALAN (APBD II) OLEH SATUAN KERJA DINAS PEKERJAAN UMUM KOTA MAKASSAR TAHUN ANGGARAN 2014 · fine IDR 1,208,483,000 · barred from tenders for 2 years · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 September 2016 · case 19/KPPU-I/2015 · PELELANGAN REHABILITASI/PEMELIHARAAN JALAN (APBD II) OLEH SATUAN KERJA DINAS PEKERJAAN UMUM KOTA MAKASSAR TAHUN ANGGARAN 2014 · fine IDR 212,746,000 · barred from tenders for 2 years · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 September 2016 · case 19/KPPU-I/2015 · PELELANGAN REHABILITASI/PEMELIHARAAN JALAN (APBD II) OLEH SATUAN KERJA DINAS PEKERJAAN UMUM KOTA MAKASSAR TAHUN ANGGARAN 2014 · fine IDR 540,562,000 · barred from tenders for 2 years · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 September 2016 · case 01/KPPU-L/2016 · PEKERJAAN PENINGKATAN JALAN PESUT PADA SATUAN KERJA DINAS BINA MARGA DAN SUMBER DAYA AIR KABUPATEN KUTAI KARTANEGARA TAHUN ANGGARAN 2015 · fine IDR 1,927,965,395 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 September 2016 · case 01/KPPU-L/2016 · PEKERJAAN PENINGKATAN JALAN PESUT PADA SATUAN KERJA DINAS BINA MARGA DAN SUMBER DAYA AIR KABUPATEN KUTAI KARTANEGARA TAHUN ANGGARAN 2015 · fine IDR 942,560,860 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 September 2016 · case 01/KPPU-L/2016 · PEKERJAAN PENINGKATAN JALAN PESUT PADA SATUAN KERJA DINAS BINA MARGA DAN SUMBER DAYA AIR KABUPATEN KUTAI KARTANEGARA TAHUN ANGGARAN 2015 · fine IDR 385,593,079 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 September 2016 · case 01/KPPU-L/2016 · PEKERJAAN PENINGKATAN JALAN PESUT PADA SATUAN KERJA DINAS BINA MARGA DAN SUMBER DAYA AIR KABUPATEN KUTAI KARTANEGARA TAHUN ANGGARAN 2015 · fine IDR 942,560,860 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Lombok Infrastruktur Perkasa
Authority Indonesia Competition Commission (KPPU) · From 30 August 2016 · case 20/KPPU-L/2015 · BERKAITAN DENGAN TENDER PENGADAAN BARANG/JASA KONSTRUKSI DI LINGKUNGAN SATUAN KERJA PELAKSANA JALAN NASIONAL WILAYAH I PROVINSI NUSA TENGGARA BARAT TAHUN ANGGARAN 2015 · fine IDR 9,056,479,194 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 August 2016 · case 20/KPPU-L/2015 · BERKAITAN DENGAN TENDER PENGADAAN BARANG/JASA KONSTRUKSI DI LINGKUNGAN SATUAN KERJA PELAKSANA JALAN NASIONAL WILAYAH I PROVINSI NUSA TENGGARA BARAT TAHUN ANGGARAN 2015 · fine IDR 3,027,656,394 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 August 2016 · case 20/KPPU-L/2015 · BERKAITAN DENGAN TENDER PENGADAAN BARANG/JASA KONSTRUKSI DI LINGKUNGAN SATUAN KERJA PELAKSANA JALAN NASIONAL WILAYAH I PROVINSI NUSA TENGGARA BARAT TAHUN ANGGARAN 2015 · fine IDR 2,029,778,604 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 August 2016 · case 15/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PENERANGAN JALAN UMUM (PJU) SIDOARJO, TAHUN ANGGARAN 2014 DAN TAHUN ANGGARAN 2015 · fine IDR 4,752,570,123 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 August 2016 · case 15/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PENERANGAN JALAN UMUM (PJU) SIDOARJO, TAHUN ANGGARAN 2014 DAN TAHUN ANGGARAN 2015 · fine IDR 370,611,318 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 August 2016 · case 15/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PENERANGAN JALAN UMUM (PJU) SIDOARJO, TAHUN ANGGARAN 2014 DAN TAHUN ANGGARAN 2015 · fine IDR 137,564,655 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Jasmanie Elektrindo Perkasa
Authority Indonesia Competition Commission (KPPU) · From 7 August 2016 · case 15/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PENERANGAN JALAN UMUM (PJU) SIDOARJO, TAHUN ANGGARAN 2014 DAN TAHUN ANGGARAN 2015 · fine IDR 357,573,682 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 August 2016 · case 15/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PENERANGAN JALAN UMUM (PJU) SIDOARJO, TAHUN ANGGARAN 2014 DAN TAHUN ANGGARAN 2015 · fine IDR 189,353,365 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 August 2016 · case 15/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PENERANGAN JALAN UMUM (PJU) SIDOARJO, TAHUN ANGGARAN 2014 DAN TAHUN ANGGARAN 2015 · fine IDR 2,057,866,945 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 August 2016 · case 15/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PENERANGAN JALAN UMUM (PJU) SIDOARJO, TAHUN ANGGARAN 2014 DAN TAHUN ANGGARAN 2015 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 June 2016 · case 13/KPPU-L/2015 · PELELANGAN PEKERJAAN PEMBANGUNAN KANTOR PEMERINTAH TAHAP II DINAS PEKERJAAN UMUM KABUPATEN NIAS SELATAN TAHUN ANGGARAN 2014 · fine IDR 2 · barred from tenders for 2 years · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 June 2016 · case 13/KPPU-L/2015 · PELELANGAN PEKERJAAN PEMBANGUNAN KANTOR PEMERINTAH TAHAP II DINAS PEKERJAAN UMUM KABUPATEN NIAS SELATAN TAHUN ANGGARAN 2014 · fine IDR 1,780,000,000 · barred from tenders for 2 years · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 June 2016 · case 12/KPPU-L/2015 · PENGADAAN BADAN USAHA SECARA PELELANGAN UMUM DALAM RANGKA PEMBANGUNAN INFRASTRUKTUR PENGOLAHAN SAMPAH BERBASIS TEKNOLOGI RAMAH LINGKUNGAN MELALUI MEKANISME KERJASAMA PEMERINTAH DAERAH DENGAN BADAN USAHA · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Perusahaan Daerah Kebersihan Kota Bandung
Authority Indonesia Competition Commission (KPPU) · From 7 June 2016 · case 12/KPPU-L/2015 · PENGADAAN BADAN USAHA SECARA PELELANGAN UMUM DALAM RANGKA PEMBANGUNAN INFRASTRUKTUR PENGOLAHAN SAMPAH BERBASIS TEKNOLOGI RAMAH LINGKUNGAN MELALUI MEKANISME KERJASAMA PEMERINTAH DAERAH DENGAN BADAN USAHA · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 May 2016 · case 11/KPPU-L/2015 · PELELANGAN 2 PAKET REKONSTRUKSI JALAN DI LINGKUNGAN SATUAN KERJA PELAKSANAAN JALAN NASIONAL DAN SATUAN KERJA PERANGKAT DAERAH WILAYAH PROVINSI GORONTALO TAHUN ANGGARAN 2014 · fine IDR 331,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 May 2016 · case 11/KPPU-L/2015 · PELELANGAN 2 PAKET REKONSTRUKSI JALAN DI LINGKUNGAN SATUAN KERJA PELAKSANAAN JALAN NASIONAL DAN SATUAN KERJA PERANGKAT DAERAH WILAYAH PROVINSI GORONTALO TAHUN ANGGARAN 2014 · fine IDR 630,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 May 2016 · case 11/KPPU-L/2015 · PELELANGAN 2 PAKET REKONSTRUKSI JALAN DI LINGKUNGAN SATUAN KERJA PELAKSANAAN JALAN NASIONAL DAN SATUAN KERJA PERANGKAT DAERAH WILAYAH PROVINSI GORONTALO TAHUN ANGGARAN 2014 · fine IDR 106,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 March 2016 · case 09/KPPU-I/2015 · PELELANGAN PAKET PEMBANGUNAN TERMINAL CONTAINER-CT3 PADA SATKER BADAN PENGUSAHAAN KAWASAN PERDAGANGAN BEBAS DAN PELABUHAN BEBAS (BPKS) SABANG TAHUN ANGGARAN 2014 · fine IDR 599,479,760 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 March 2016 · case 09/KPPU-I/2015 · PELELANGAN PAKET PEMBANGUNAN TERMINAL CONTAINER-CT3 PADA SATKER BADAN PENGUSAHAAN KAWASAN PERDAGANGAN BEBAS DAN PELABUHAN BEBAS (BPKS) SABANG TAHUN ANGGARAN 2014 · fine IDR 199,866,552 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 March 2016 · case 09/KPPU-I/2015 · PELELANGAN PAKET PEMBANGUNAN TERMINAL CONTAINER-CT3 PADA SATKER BADAN PENGUSAHAAN KAWASAN PERDAGANGAN BEBAS DAN PELABUHAN BEBAS (BPKS) SABANG TAHUN ANGGARAN 2014 · fine IDR 199,866,552 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 March 2016 · case 09/KPPU-I/2015 · PELELANGAN PAKET PEMBANGUNAN TERMINAL CONTAINER-CT3 PADA SATKER BADAN PENGUSAHAAN KAWASAN PERDAGANGAN BEBAS DAN PELABUHAN BEBAS (BPKS) SABANG TAHUN ANGGARAN 2014 · fine IDR 199,866,552 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 872,367,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 826,269,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 797,572,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 593,742,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 57,652,000 · respondent IX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 353,211,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 258,974,000 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 316,823,000 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 99,610,000 · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 48,782,000 · respondent X of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 5,037,427,000 · respondent XI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 5,748,520,000 · respondent XII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 851,924,000 · respondent XIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Sinarindo Wiranusa Elektrik
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 5,641,935,000 · respondent XIV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 781,526,000 · respondent XV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 1,821,205,000 · respondent XVI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 February 2016 · case 07/KPPU-L/2015 · PELELANGAN PAKET-PAKET PEKERJAAN HUTM, HUTR, DAN TRAFO DISTRIBUSI DI PT PLN (PERSERO) UNIT PELAKSANA KONSTRUKSI KELISTRIKAN SATUAN KERJA LISTRIK PERDESAAN SUMATERA UTARA, APBN TAHUN ANGGARAN 2013 · fine IDR 176,764,000 · respondent XVII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 January 2016 · case 05/KPPU-L/2015 · TENDER REHAB/PEMELIHARAAN JALAN LINGKAR TIMUR KOTA PRABUMULIH PROVINSI SUMATERA SELATAN TAHUN ANGGARAN 2013 · fine IDR 1,446,151,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 January 2016 · case 05/KPPU-L/2015 · TENDER REHAB/PEMELIHARAAN JALAN LINGKAR TIMUR KOTA PRABUMULIH PROVINSI SUMATERA SELATAN TAHUN ANGGARAN 2013 · fine IDR 850,677,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 January 2016 · case 05/KPPU-L/2015 · TENDER REHAB/PEMELIHARAAN JALAN LINGKAR TIMUR KOTA PRABUMULIH PROVINSI SUMATERA SELATAN TAHUN ANGGARAN 2013 · fine IDR 935,745,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 January 2016 · case 05/KPPU-L/2015 · TENDER REHAB/PEMELIHARAAN JALAN LINGKAR TIMUR KOTA PRABUMULIH PROVINSI SUMATERA SELATAN TAHUN ANGGARAN 2013 · fine IDR 935,745,000 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 January 2016 · case 05/KPPU-L/2015 · TENDER REHAB/PEMELIHARAAN JALAN LINGKAR TIMUR KOTA PRABUMULIH PROVINSI SUMATERA SELATAN TAHUN ANGGARAN 2013 · barred from tenders for 2 years · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 December 2015 · case 04/KPPU-L/2015 · PAKET PELEBARAN JALAN BATAS PROPINSI JAWA BARAT-PATIMUAN-SIDAREJA DAN PAKET PELEBARAN JALAN SIDAREJA-JERUKLEGI, WILAYAH I JAWA TENGAH, PROVINSI JAWA TENGAH TAHUN ANGGARAN 2013 · fine IDR 1,669,582,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 December 2015 · case 04/KPPU-L/2015 · PAKET PELEBARAN JALAN BATAS PROPINSI JAWA BARAT-PATIMUAN-SIDAREJA DAN PAKET PELEBARAN JALAN SIDAREJA-JERUKLEGI, WILAYAH I JAWA TENGAH, PROVINSI JAWA TENGAH TAHUN ANGGARAN 2013 · fine IDR 1,660,210,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 December 2015 · case 04/KPPU-L/2015 · PAKET PELEBARAN JALAN BATAS PROPINSI JAWA BARAT-PATIMUAN-SIDAREJA DAN PAKET PELEBARAN JALAN SIDAREJA-JERUKLEGI, WILAYAH I JAWA TENGAH, PROVINSI JAWA TENGAH TAHUN ANGGARAN 2013 · fine IDR 1,660,210,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 December 2015 · case 04/KPPU-L/2015 · PAKET PELEBARAN JALAN BATAS PROPINSI JAWA BARAT-PATIMUAN-SIDAREJA DAN PAKET PELEBARAN JALAN SIDAREJA-JERUKLEGI, WILAYAH I JAWA TENGAH, PROVINSI JAWA TENGAH TAHUN ANGGARAN 2013 · fine IDR 369,976,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 December 2015 · case 04/KPPU-L/2015 · PAKET PELEBARAN JALAN BATAS PROPINSI JAWA BARAT-PATIMUAN-SIDAREJA DAN PAKET PELEBARAN JALAN SIDAREJA-JERUKLEGI, WILAYAH I JAWA TENGAH, PROVINSI JAWA TENGAH TAHUN ANGGARAN 2013 · barred from tenders for 2 years · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 December 2015 · case 03/KPPU-L/2015 · BERKAITAN DENGAN TENDER PEKERJAAN PELEBARAN JALAN MEREK – BTS. KAB. SIMALUNGUN – BTS. KAB. TANAH KARO – SERIBU DOLOK PADA KELOMPOK KERJA (POKJA) PENGADAAN BARANG/JASA SATUAN KERJA PELAKSANAAN JALAN NASIONAL WILAYAH I PROPINSI SUMATERA UTARA TAHUN ANGGARAN 2013 · fine IDR 3,750,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 December 2015 · case 03/KPPU-L/2015 · BERKAITAN DENGAN TENDER PEKERJAAN PELEBARAN JALAN MEREK – BTS. KAB. SIMALUNGUN – BTS. KAB. TANAH KARO – SERIBU DOLOK PADA KELOMPOK KERJA (POKJA) PENGADAAN BARANG/JASA SATUAN KERJA PELAKSANAAN JALAN NASIONAL WILAYAH I PROPINSI SUMATERA UTARA TAHUN ANGGARAN 2013 · fine IDR 2,000,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 December 2015 · case 03/KPPU-L/2015 · BERKAITAN DENGAN TENDER PEKERJAAN PELEBARAN JALAN MEREK – BTS. KAB. SIMALUNGUN – BTS. KAB. TANAH KARO – SERIBU DOLOK PADA KELOMPOK KERJA (POKJA) PENGADAAN BARANG/JASA SATUAN KERJA PELAKSANAAN JALAN NASIONAL WILAYAH I PROPINSI SUMATERA UTARA TAHUN ANGGARAN 2013 · fine IDR 125,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 December 2015 · case 06/KPPU-L/2015 · TENDER PEMBANGUNAN GEDUNG DPRD KABUPATEN BARITO KUALA DAN LAND DEVELOPMENTNYA TAHUN ANGGARAN 2013-2015 (MULTIYEARS) · fine IDR 242,002,360 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 December 2015 · case 06/KPPU-L/2015 · TENDER PEMBANGUNAN GEDUNG DPRD KABUPATEN BARITO KUALA DAN LAND DEVELOPMENTNYA TAHUN ANGGARAN 2013-2015 (MULTIYEARS) · fine IDR 121,001,180 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 7 December 2015 · case 06/KPPU-L/2015 · TENDER PEMBANGUNAN GEDUNG DPRD KABUPATEN BARITO KUALA DAN LAND DEVELOPMENTNYA TAHUN ANGGARAN 2013-2015 (MULTIYEARS) · fine IDR 40,333,726 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 September 2015 · case 02/KPPU-L/2015 · DENGAN PELELANGAN 4 (EMPAT) PAKET PEKERJAAN DI LINGKUNGAN KONSTRUKSI SNVT PELAKSANAAN JALAN NASIONAL PROVINSI KEPULAUAN RIAU, ULP BALAI BESAR PELAKSANAAN JALAN NASIONAL II KEMENTERIAN PEKERJAAN UMUM DENGAN SISTEM FULL-PROCUREMENT TAHUN ANGGARAN 2014 · fine IDR 1,730,300,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 September 2015 · case 02/KPPU-L/2015 · DENGAN PELELANGAN 4 (EMPAT) PAKET PEKERJAAN DI LINGKUNGAN KONSTRUKSI SNVT PELAKSANAAN JALAN NASIONAL PROVINSI KEPULAUAN RIAU, ULP BALAI BESAR PELAKSANAAN JALAN NASIONAL II KEMENTERIAN PEKERJAAN UMUM DENGAN SISTEM FULL-PROCUREMENT TAHUN ANGGARAN 2014 · fine IDR 1,948,650,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 September 2015 · case 02/KPPU-L/2015 · DENGAN PELELANGAN 4 (EMPAT) PAKET PEKERJAAN DI LINGKUNGAN KONSTRUKSI SNVT PELAKSANAAN JALAN NASIONAL PROVINSI KEPULAUAN RIAU, ULP BALAI BESAR PELAKSANAAN JALAN NASIONAL II KEMENTERIAN PEKERJAAN UMUM DENGAN SISTEM FULL-PROCUREMENT TAHUN ANGGARAN 2014 · fine IDR 648,457,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 September 2015 · case 02/KPPU-L/2015 · DENGAN PELELANGAN 4 (EMPAT) PAKET PEKERJAAN DI LINGKUNGAN KONSTRUKSI SNVT PELAKSANAAN JALAN NASIONAL PROVINSI KEPULAUAN RIAU, ULP BALAI BESAR PELAKSANAAN JALAN NASIONAL II KEMENTERIAN PEKERJAAN UMUM DENGAN SISTEM FULL-PROCUREMENT TAHUN ANGGARAN 2014 · fine IDR 618,050,000 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 September 2015 · case 02/KPPU-L/2015 · DENGAN PELELANGAN 4 (EMPAT) PAKET PEKERJAAN DI LINGKUNGAN KONSTRUKSI SNVT PELAKSANAAN JALAN NASIONAL PROVINSI KEPULAUAN RIAU, ULP BALAI BESAR PELAKSANAAN JALAN NASIONAL II KEMENTERIAN PEKERJAAN UMUM DENGAN SISTEM FULL-PROCUREMENT TAHUN ANGGARAN 2014 · fine IDR 386,390,000 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 September 2015 · case 02/KPPU-L/2015 · DENGAN PELELANGAN 4 (EMPAT) PAKET PEKERJAAN DI LINGKUNGAN KONSTRUKSI SNVT PELAKSANAAN JALAN NASIONAL PROVINSI KEPULAUAN RIAU, ULP BALAI BESAR PELAKSANAAN JALAN NASIONAL II KEMENTERIAN PEKERJAAN UMUM DENGAN SISTEM FULL-PROCUREMENT TAHUN ANGGARAN 2014 · fine IDR 96,590,000 · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 August 2015 · case 01/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PADA DINAS PEKERJAAN UMUM, KABUPATEN ASAHAN, SUMATERA UTARA, TAHUN ANGGARAN 2013 · barred from tenders for 2 years · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 August 2015 · case 01/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PADA DINAS PEKERJAAN UMUM, KABUPATEN ASAHAN, SUMATERA UTARA, TAHUN ANGGARAN 2013 · barred from tenders for 2 years · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 August 2015 · case 01/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PADA DINAS PEKERJAAN UMUM, KABUPATEN ASAHAN, SUMATERA UTARA, TAHUN ANGGARAN 2013 · barred from tenders for 2 years · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 August 2015 · case 01/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PADA DINAS PEKERJAAN UMUM, KABUPATEN ASAHAN, SUMATERA UTARA, TAHUN ANGGARAN 2013 · barred from tenders for 2 years · respondent IX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 August 2015 · case 01/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PADA DINAS PEKERJAAN UMUM, KABUPATEN ASAHAN, SUMATERA UTARA, TAHUN ANGGARAN 2013 · barred from tenders for 2 years · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 August 2015 · case 01/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PADA DINAS PEKERJAAN UMUM, KABUPATEN ASAHAN, SUMATERA UTARA, TAHUN ANGGARAN 2013 · barred from tenders for 2 years · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 August 2015 · case 01/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PADA DINAS PEKERJAAN UMUM, KABUPATEN ASAHAN, SUMATERA UTARA, TAHUN ANGGARAN 2013 · barred from tenders for 2 years · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 August 2015 · case 01/KPPU-L/2015 · 5 (LIMA) PAKET TENDER PADA DINAS PEKERJAAN UMUM, KABUPATEN ASAHAN, SUMATERA UTARA, TAHUN ANGGARAN 2013 · barred from tenders for 2 years · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 3,064,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 9,158,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Industri Kereta Api (Persero)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 4,938,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 5,040,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 2,225,000,000 · respondent IX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 4,044,000,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 2,832,000,000 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 3,620,000,000 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 5,175,000,000 · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 937,000,000 · respondent X of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · barred from tenders for 2 years · respondent XI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 1,425,000,000 · respondent XII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 910,000,000 · respondent XIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 302,000,000 · respondent XIV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Transportindo Bakti Nusantara
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · barred from tenders for 2 years · respondent XV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 818,000,000 · respondent XVI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 99,000,000 · respondent XVII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 August 2015 · case 15/KPPU-I/2014 · PENGADAAN BUS TRANSJAKARTA (MEDIUM BUS, SINGLE BUS, DAN ARTICULATED BUS) TAHUN ANGGARAN 2013 · fine IDR 25,000,000,000 · respondent XVIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 April 2015 · case 10/KPPU-L/2014 · DALAM PELANGGARAN PASAL 22 UNDANG-UNDANG NOMOR 5 TAHUN 1999 DI PENGADAAN BARANG CETAKAN DAN PENGGANDAAN PERLENGKAPAN KPPS/TPS, PPS, DAN PPK PEMILIHAN GUBERNUR DAN WAKIL GUBERNUR SULAWESI SELATAN TAHUN 2013 · fine IDR 1,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 April 2015 · case 10/KPPU-L/2014 · DALAM PELANGGARAN PASAL 22 UNDANG-UNDANG NOMOR 5 TAHUN 1999 DI PENGADAAN BARANG CETAKAN DAN PENGGANDAAN PERLENGKAPAN KPPS/TPS, PPS, DAN PPK PEMILIHAN GUBERNUR DAN WAKIL GUBERNUR SULAWESI SELATAN TAHUN 2013 · fine IDR 185,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 April 2015 · case 10/KPPU-L/2014 · DALAM PELANGGARAN PASAL 22 UNDANG-UNDANG NOMOR 5 TAHUN 1999 DI PENGADAAN BARANG CETAKAN DAN PENGGANDAAN PERLENGKAPAN KPPS/TPS, PPS, DAN PPK PEMILIHAN GUBERNUR DAN WAKIL GUBERNUR SULAWESI SELATAN TAHUN 2013 · fine IDR 193,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 April 2015 · case 10/KPPU-L/2014 · DALAM PELANGGARAN PASAL 22 UNDANG-UNDANG NOMOR 5 TAHUN 1999 DI PENGADAAN BARANG CETAKAN DAN PENGGANDAAN PERLENGKAPAN KPPS/TPS, PPS, DAN PPK PEMILIHAN GUBERNUR DAN WAKIL GUBERNUR SULAWESI SELATAN TAHUN 2013 · fine IDR 138,000,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 14 April 2015 · case 16/KPPU-L/2014 · PENGADAAN SARANA PENINGKATAN MUTU PENDIDIKAN DI SD/SDLB DI DINAS PENIDIDIKAN KABUPATEN PROBOLINGGO, JAWA TIMUR TAHUN ANGGARAN 2012 · fine IDR 457,733,600 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 14 April 2015 · case 16/KPPU-L/2014 · PENGADAAN SARANA PENINGKATAN MUTU PENDIDIKAN DI SD/SDLB DI DINAS PENIDIDIKAN KABUPATEN PROBOLINGGO, JAWA TIMUR TAHUN ANGGARAN 2012 · fine IDR 130,781,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 April 2015 · case 18/KPPU-L/2014 · TENDER PENGADAAN KERAMBA JARING APUNG HIGH DENSITY POLYETHYLENE (HDPE) DI LINGKUNGAN POKJA 7 UNIT LAYANAN PENGADAAN PEMERINTAH PROVINSI KEPULAUAN RIAU TAHUN ANGGARAN 2012 · fine IDR 946,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 April 2015 · case 18/KPPU-L/2014 · TENDER PENGADAAN KERAMBA JARING APUNG HIGH DENSITY POLYETHYLENE (HDPE) DI LINGKUNGAN POKJA 7 UNIT LAYANAN PENGADAAN PEMERINTAH PROVINSI KEPULAUAN RIAU TAHUN ANGGARAN 2012 · fine IDR 105,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 24 March 2015 · case 19/KPPU-L/2014 · BERKAITAN DENGAN TENDER PEKERJAAN REVITALISASI PEMBANGUNAN GELANGGANG PEMUDA/ REMAJA PROPINSI NUSA TENGGARA BARAT TAHUN ANGGARAN 2011 · fine IDR 816,786,102 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 28 January 2015 · case 17/KPPU-L/2014 · TENDER PEMBANGUNAN GEDUNG (PARUGA) SAMAKAI KABUPATEN DOMPU PROPINSI NUSA TENGGARA BARAT TAHUN ANGGARAN 2014 · fine IDR 332,000,000 · barred from tenders for 1 year · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 28 January 2015 · case 17/KPPU-L/2014 · TENDER PEMBANGUNAN GEDUNG (PARUGA) SAMAKAI KABUPATEN DOMPU PROPINSI NUSA TENGGARA BARAT TAHUN ANGGARAN 2014 · barred from tenders for 1 year · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 28 January 2015 · case 17/KPPU-L/2014 · TENDER PEMBANGUNAN GEDUNG (PARUGA) SAMAKAI KABUPATEN DOMPU PROPINSI NUSA TENGGARA BARAT TAHUN ANGGARAN 2014 · barred from tenders for 1 year · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 January 2015 · case 11/KPPU-L/2014 · DUA PAKET LELANG PADA DINAS PEKERJAAN UMUM BINA MARGA KEGIATAN JALAN DAN JEMBATAN PEMERINTAH KABUPATEN OGAN ILIR PROPINSI SUMATERA SELATAN TAHUN ANGGARAN 2013 · fine IDR 1,533,000,000 · barred from tenders for 1 year · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 January 2015 · case 11/KPPU-L/2014 · DUA PAKET LELANG PADA DINAS PEKERJAAN UMUM BINA MARGA KEGIATAN JALAN DAN JEMBATAN PEMERINTAH KABUPATEN OGAN ILIR PROPINSI SUMATERA SELATAN TAHUN ANGGARAN 2013 · fine IDR 1,254,000,000 · barred from tenders for 1 year · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 January 2015 · case 11/KPPU-L/2014 · DUA PAKET LELANG PADA DINAS PEKERJAAN UMUM BINA MARGA KEGIATAN JALAN DAN JEMBATAN PEMERINTAH KABUPATEN OGAN ILIR PROPINSI SUMATERA SELATAN TAHUN ANGGARAN 2013 · fine IDR 1,254,000,000 · barred from tenders for 1 year · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 January 2015 · case 11/KPPU-L/2014 · DUA PAKET LELANG PADA DINAS PEKERJAAN UMUM BINA MARGA KEGIATAN JALAN DAN JEMBATAN PEMERINTAH KABUPATEN OGAN ILIR PROPINSI SUMATERA SELATAN TAHUN ANGGARAN 2013 · fine IDR 352,000,000 · barred from tenders for 1 year · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 21 January 2015 · case 11/KPPU-L/2014 · DUA PAKET LELANG PADA DINAS PEKERJAAN UMUM BINA MARGA KEGIATAN JALAN DAN JEMBATAN PEMERINTAH KABUPATEN OGAN ILIR PROPINSI SUMATERA SELATAN TAHUN ANGGARAN 2013 · fine IDR 100,000,000 · barred from tenders for 1 year · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 December 2014 · case 09/KPPU-L/2014 · PELELANGAN UMUM PENGADAAN JASA KONSTRUKSI 3 PAKET REHABILITASI/PEMELIHARAAN JALAN DAN PEMBANGUNAN JALAN DI KAB. MINAHASA UTARA, PROVINSI SULAWESI UTARA TA 2011 & 2012 · fine IDR 1,100,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 December 2014 · case 09/KPPU-L/2014 · PELELANGAN UMUM PENGADAAN JASA KONSTRUKSI 3 PAKET REHABILITASI/PEMELIHARAAN JALAN DAN PEMBANGUNAN JALAN DI KAB. MINAHASA UTARA, PROVINSI SULAWESI UTARA TA 2011 & 2012 · fine IDR 375,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 December 2014 · case 09/KPPU-L/2014 · PELELANGAN UMUM PENGADAAN JASA KONSTRUKSI 3 PAKET REHABILITASI/PEMELIHARAAN JALAN DAN PEMBANGUNAN JALAN DI KAB. MINAHASA UTARA, PROVINSI SULAWESI UTARA TA 2011 & 2012 · fine IDR 295,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 December 2014 · case 09/KPPU-L/2014 · PELELANGAN UMUM PENGADAAN JASA KONSTRUKSI 3 PAKET REHABILITASI/PEMELIHARAAN JALAN DAN PEMBANGUNAN JALAN DI KAB. MINAHASA UTARA, PROVINSI SULAWESI UTARA TA 2011 & 2012 · fine IDR 153,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 November 2014 · case 06/KPPU-L/2014 · PELELANGAN PEMBANGUNAN ASRAMA MA – HAD ALI SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANG SIDEMPUAN, SUMATERA UTARA SUMBER DANA PEMANFAATAN PENGHEMATAN KEMENTERIAN AGAMA REPUBLIK INDONESIA APBN TAHUN ANGGARAN 2011 DAN 2012 YANG DILAKUKAN OLEH POKJA PENGADAAN BARANG/JASA SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANGSIDEMPUAN, PT WIRA KARYA DUTA UTAMA, PT HARIDA JAYA, PT WIRA INDO KARYA UTAMA DAN PT WELLY KARYA NUSANTARA · fine IDR 80,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 November 2014 · case 06/KPPU-L/2014 · PELELANGAN PEMBANGUNAN ASRAMA MA – HAD ALI SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANG SIDEMPUAN, SUMATERA UTARA SUMBER DANA PEMANFAATAN PENGHEMATAN KEMENTERIAN AGAMA REPUBLIK INDONESIA APBN TAHUN ANGGARAN 2011 DAN 2012 YANG DILAKUKAN OLEH POKJA PENGADAAN BARANG/JASA SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANGSIDEMPUAN, PT WIRA KARYA DUTA UTAMA, PT HARIDA JAYA, PT WIRA INDO KARYA UTAMA DAN PT WELLY KARYA NUSANTARA · fine IDR 103,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 November 2014 · case 06/KPPU-L/2014 · PELELANGAN PEMBANGUNAN ASRAMA MA – HAD ALI SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANG SIDEMPUAN, SUMATERA UTARA SUMBER DANA PEMANFAATAN PENGHEMATAN KEMENTERIAN AGAMA REPUBLIK INDONESIA APBN TAHUN ANGGARAN 2011 DAN 2012 YANG DILAKUKAN OLEH POKJA PENGADAAN BARANG/JASA SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANGSIDEMPUAN, PT WIRA KARYA DUTA UTAMA, PT HARIDA JAYA, PT WIRA INDO KARYA UTAMA DAN PT WELLY KARYA NUSANTARA · fine IDR 211,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 November 2014 · case 06/KPPU-L/2014 · PELELANGAN PEMBANGUNAN ASRAMA MA – HAD ALI SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANG SIDEMPUAN, SUMATERA UTARA SUMBER DANA PEMANFAATAN PENGHEMATAN KEMENTERIAN AGAMA REPUBLIK INDONESIA APBN TAHUN ANGGARAN 2011 DAN 2012 YANG DILAKUKAN OLEH POKJA PENGADAAN BARANG/JASA SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANGSIDEMPUAN, PT WIRA KARYA DUTA UTAMA, PT HARIDA JAYA, PT WIRA INDO KARYA UTAMA DAN PT WELLY KARYA NUSANTARA · fine IDR 80,000,000 · respondent IX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 November 2014 · case 06/KPPU-L/2014 · PELELANGAN PEMBANGUNAN ASRAMA MA – HAD ALI SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANG SIDEMPUAN, SUMATERA UTARA SUMBER DANA PEMANFAATAN PENGHEMATAN KEMENTERIAN AGAMA REPUBLIK INDONESIA APBN TAHUN ANGGARAN 2011 DAN 2012 YANG DILAKUKAN OLEH POKJA PENGADAAN BARANG/JASA SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANGSIDEMPUAN, PT WIRA KARYA DUTA UTAMA, PT HARIDA JAYA, PT WIRA INDO KARYA UTAMA DAN PT WELLY KARYA NUSANTARA · fine IDR 108,000,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 November 2014 · case 06/KPPU-L/2014 · PELELANGAN PEMBANGUNAN ASRAMA MA – HAD ALI SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANG SIDEMPUAN, SUMATERA UTARA SUMBER DANA PEMANFAATAN PENGHEMATAN KEMENTERIAN AGAMA REPUBLIK INDONESIA APBN TAHUN ANGGARAN 2011 DAN 2012 YANG DILAKUKAN OLEH POKJA PENGADAAN BARANG/JASA SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANGSIDEMPUAN, PT WIRA KARYA DUTA UTAMA, PT HARIDA JAYA, PT WIRA INDO KARYA UTAMA DAN PT WELLY KARYA NUSANTARA · fine IDR 88,000,000 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 November 2014 · case 06/KPPU-L/2014 · PELELANGAN PEMBANGUNAN ASRAMA MA – HAD ALI SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANG SIDEMPUAN, SUMATERA UTARA SUMBER DANA PEMANFAATAN PENGHEMATAN KEMENTERIAN AGAMA REPUBLIK INDONESIA APBN TAHUN ANGGARAN 2011 DAN 2012 YANG DILAKUKAN OLEH POKJA PENGADAAN BARANG/JASA SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANGSIDEMPUAN, PT WIRA KARYA DUTA UTAMA, PT HARIDA JAYA, PT WIRA INDO KARYA UTAMA DAN PT WELLY KARYA NUSANTARA · fine IDR 108,000,000 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 November 2014 · case 06/KPPU-L/2014 · PELELANGAN PEMBANGUNAN ASRAMA MA – HAD ALI SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANG SIDEMPUAN, SUMATERA UTARA SUMBER DANA PEMANFAATAN PENGHEMATAN KEMENTERIAN AGAMA REPUBLIK INDONESIA APBN TAHUN ANGGARAN 2011 DAN 2012 YANG DILAKUKAN OLEH POKJA PENGADAAN BARANG/JASA SEKOLAH TINGGI AGAMA ISLAM NEGERI (STAIN) PADANGSIDEMPUAN, PT WIRA KARYA DUTA UTAMA, PT HARIDA JAYA, PT WIRA INDO KARYA UTAMA DAN PT WELLY KARYA NUSANTARA · fine IDR 80,000,000 · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 28 August 2014 · case 12/KPPU-L/2013 · DUGAAN PELANGGARAN UNDANG - UNDANG NO. 5 TAHUN 1999 TERKAIT TENDER PEMBUKAAN/PEMBANGUNAN JALAN TANJUNG AGUNG - SIMPANG PAGAR AGUNG - DANAU LIANG DI KABUPATEN LEBONG PROVINSI BENGKULU TA 2011 · fine IDR 29,000,000 · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 12 June 2014 · case 10/KPPU-L/2013 · (SELANJUTNYA DISEBUT UNDANG-UNDANG NO. 5 TAHUN 1999) TERKAIT TENDER PENGADAAN ALAT KEDOKTERAN, KESEHATAN DAN KB DI RUMAH SAKIT UMUM DAERAH (RSUD) EMBUNG FATIMAH KOTA BATAM TAHUN ANGGARAN 2011 · fine IDR 900,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 12 June 2014 · case 10/KPPU-L/2013 · (SELANJUTNYA DISEBUT UNDANG-UNDANG NO. 5 TAHUN 1999) TERKAIT TENDER PENGADAAN ALAT KEDOKTERAN, KESEHATAN DAN KB DI RUMAH SAKIT UMUM DAERAH (RSUD) EMBUNG FATIMAH KOTA BATAM TAHUN ANGGARAN 2011 · fine IDR 450,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 12 June 2014 · case 10/KPPU-L/2013 · (SELANJUTNYA DISEBUT UNDANG-UNDANG NO. 5 TAHUN 1999) TERKAIT TENDER PENGADAAN ALAT KEDOKTERAN, KESEHATAN DAN KB DI RUMAH SAKIT UMUM DAERAH (RSUD) EMBUNG FATIMAH KOTA BATAM TAHUN ANGGARAN 2011 · fine IDR 100,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 14 April 2014 · case 08/KPPU-L/2013 · TENDER PENGADAAN PERALATAN CT SCAN DI RSUD DR. PIRNGADI KOTA MEDAN TAHUN ANGGARAN 2012 · fine IDR 528,556,700 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 14 April 2014 · case 08/KPPU-L/2013 · TENDER PENGADAAN PERALATAN CT SCAN DI RSUD DR. PIRNGADI KOTA MEDAN TAHUN ANGGARAN 2012 · fine IDR 264,278,350 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 14 April 2014 · case 08/KPPU-L/2013 · TENDER PENGADAAN PERALATAN CT SCAN DI RSUD DR. PIRNGADI KOTA MEDAN TAHUN ANGGARAN 2012 · fine IDR 158,567,010 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 14 April 2014 · case 08/KPPU-L/2013 · TENDER PENGADAAN PERALATAN CT SCAN DI RSUD DR. PIRNGADI KOTA MEDAN TAHUN ANGGARAN 2012 · fine IDR 52,855,670 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 January 2014 · case 04/KPPU-L/2013 · TENDER PENGADAAN ALAT BERAT/ALAT BANTU DI BALAI PELAKSANAAN JALAN NASIONAL VIII DIREKTORAT JENDERAL BINA MARGA KEMENTERIAN PEKERJAAN UMUM TAHUN ANGGARAN 2011 · fine IDR 1,952,280,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 January 2014 · case 04/KPPU-L/2013 · TENDER PENGADAAN ALAT BERAT/ALAT BANTU DI BALAI PELAKSANAAN JALAN NASIONAL VIII DIREKTORAT JENDERAL BINA MARGA KEMENTERIAN PEKERJAAN UMUM TAHUN ANGGARAN 2011 · fine IDR 1,952,280,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 October 2013 · case 03/KPPU-L/2013 · TENDER PENGADAAN 30 UNIT TRAKTOR BESAR DI BADAN PENANGGULANGAN BENCANA DAERAH PROPINSI NUSA TENGGARA TIMUR TAHUN ANGGARAN 2010 · fine IDR 232,571,690 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 October 2013 · case 03/KPPU-L/2013 · TENDER PENGADAAN 30 UNIT TRAKTOR BESAR DI BADAN PENANGGULANGAN BENCANA DAERAH PROPINSI NUSA TENGGARA TIMUR TAHUN ANGGARAN 2010 · fine IDR 232,571,690 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 October 2013 · case 03/KPPU-L/2013 · TENDER PENGADAAN 30 UNIT TRAKTOR BESAR DI BADAN PENANGGULANGAN BENCANA DAERAH PROPINSI NUSA TENGGARA TIMUR TAHUN ANGGARAN 2010 · fine IDR 232,571,690 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 July 2013 · case 01/KPPU-L/2013 · TENDER PENGADAAN BARANG CETAKAN DAN ALAT PERAGA DINAS PENDIDIKAN DAERAH KABUPATEN TAPANULI SELATAN TAHUN ANGGARAN 2011 (PAKET 1 DAN PAKET 13) · fine IDR 50,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 July 2013 · case 01/KPPU-L/2013 · TENDER PENGADAAN BARANG CETAKAN DAN ALAT PERAGA DINAS PENDIDIKAN DAERAH KABUPATEN TAPANULI SELATAN TAHUN ANGGARAN 2011 (PAKET 1 DAN PAKET 13) · fine IDR 250,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 July 2013 · case 01/KPPU-L/2013 · TENDER PENGADAAN BARANG CETAKAN DAN ALAT PERAGA DINAS PENDIDIKAN DAERAH KABUPATEN TAPANULI SELATAN TAHUN ANGGARAN 2011 (PAKET 1 DAN PAKET 13) · fine IDR 50,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 12 July 2013 · case 06/KPPU-L/2012 · TENDER PEMBANGUNAN TERMINAL ALBN SEI AMBAWANG TAHAP KE XI TAHUN ANGGARAN 2012 · fine IDR 1,819,125,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 12 July 2013 · case 06/KPPU-L/2012 · TENDER PEMBANGUNAN TERMINAL ALBN SEI AMBAWANG TAHAP KE XI TAHUN ANGGARAN 2012 · fine IDR 330,750,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 12 July 2013 · case 06/KPPU-L/2012 · TENDER PEMBANGUNAN TERMINAL ALBN SEI AMBAWANG TAHAP KE XI TAHUN ANGGARAN 2012 · fine IDR 413,437,500 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 12 July 2013 · case 06/KPPU-L/2012 · TENDER PEMBANGUNAN TERMINAL ALBN SEI AMBAWANG TAHAP KE XI TAHUN ANGGARAN 2012 · fine IDR 99,225,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Asria Nurlindra Inti Sejahtera
Authority Indonesia Competition Commission (KPPU) · From 12 July 2013 · case 06/KPPU-L/2012 · TENDER PEMBANGUNAN TERMINAL ALBN SEI AMBAWANG TAHAP KE XI TAHUN ANGGARAN 2012 · fine IDR 99,225,000 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 8 July 2013 · case 07/KPPU-L/2012 · PELELANGAN UMUM BADAN HUKUM MITRA KERJA SAMA PEMBANGUNAN PASAR TRADISIONAL SEMI MODERN POLA BANGUN GUNA SERAH (BUILD OPERATE TRANSFER - BOT) DI KABUPATEN SUKABUMI TAHUN 2011 · fine IDR 10,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 8 July 2013 · case 07/KPPU-L/2012 · PELELANGAN UMUM BADAN HUKUM MITRA KERJA SAMA PEMBANGUNAN PASAR TRADISIONAL SEMI MODERN POLA BANGUN GUNA SERAH (BUILD OPERATE TRANSFER - BOT) DI KABUPATEN SUKABUMI TAHUN 2011 · fine IDR 10,000,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 8 July 2013 · case 07/KPPU-L/2012 · PELELANGAN UMUM BADAN HUKUM MITRA KERJA SAMA PEMBANGUNAN PASAR TRADISIONAL SEMI MODERN POLA BANGUN GUNA SERAH (BUILD OPERATE TRANSFER - BOT) DI KABUPATEN SUKABUMI TAHUN 2011 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 9 April 2013 · case 04/KPPU-L/2012 · DALAM TENDER PEMBANGUNAN GEDUNG PELAYANAN DAN PERAWATAN KELAS I DAN VIP RUMAH SAKIT SULAWESI TENGGARA TAHUN ANGGARAN 2011 · fine IDR 4,475,525,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 9 April 2013 · case 04/KPPU-L/2012 · DALAM TENDER PEMBANGUNAN GEDUNG PELAYANAN DAN PERAWATAN KELAS I DAN VIP RUMAH SAKIT SULAWESI TENGGARA TAHUN ANGGARAN 2011 · fine IDR 4,475,525,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 November 2012 · case 03/KPPU-L/2012 · TENDER PENERAPAN KARTU TANDA PENDUDUK BERBASIS NIK SECARA NASIONAL (KTP ELEKTRONIK) TAHUN 2011 S/D 2012 · fine IDR 4,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 November 2012 · case 03/KPPU-L/2012 · TENDER PENERAPAN KARTU TANDA PENDUDUK BERBASIS NIK SECARA NASIONAL (KTP ELEKTRONIK) TAHUN 2011 S/D 2012 · fine IDR 4,000,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 16 October 2012 · case 02/KPPU-L/2012 · TENDER PAKET PEKERJAAN DI LINGKUNGAN SATUAN KERJA PENGEMBANGAN KINERJA PENGELOLAAN AIR MINUM DI PROPINSI SUMATERA BARAT TAHUN ANGGARAN 2011 · fine IDR 513,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 16 October 2012 · case 02/KPPU-L/2012 · TENDER PAKET PEKERJAAN DI LINGKUNGAN SATUAN KERJA PENGEMBANGAN KINERJA PENGELOLAAN AIR MINUM DI PROPINSI SUMATERA BARAT TAHUN ANGGARAN 2011 · fine IDR 532,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 16 October 2012 · case 02/KPPU-L/2012 · TENDER PAKET PEKERJAAN DI LINGKUNGAN SATUAN KERJA PENGEMBANGAN KINERJA PENGELOLAAN AIR MINUM DI PROPINSI SUMATERA BARAT TAHUN ANGGARAN 2011 · fine IDR 513,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 October 2012 · case 12/KPPU-L/2011 · TENDER ULANG PAKET PEKERJAAN PENGADAAN BIBIT KAKAO SOMATIC EMBRIOGENESIS (SE) DENGAN SUMBER DANA APBN MELALUI DIPA BAGIAN ANGGARAN 999 TAHUN ANGGARAN 2010 SATUAN KERJA DINAS PERKEBUNAN PROVINSI SULAWESI BARAT · fine IDR 600,000,000 · barred from tenders for 1 year · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 October 2012 · case 12/KPPU-L/2011 · TENDER ULANG PAKET PEKERJAAN PENGADAAN BIBIT KAKAO SOMATIC EMBRIOGENESIS (SE) DENGAN SUMBER DANA APBN MELALUI DIPA BAGIAN ANGGARAN 999 TAHUN ANGGARAN 2010 SATUAN KERJA DINAS PERKEBUNAN PROVINSI SULAWESI BARAT · barred from tenders for 1 year · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 June 2012 · case 13/KPPU-L/2011 · PELELANGAN PAKET PEKERJAAN PEMBANGUNAN JALAN SP. MUTIARA-PESISIR SELATAN DI LINGKUNGAN DINAS PEKERJAAN UMUM KABUPATEN KARIMUN PROVINSI KEPULAUAN RIAU TAHUN ANGGARAN 2011 · fine IDR 250,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 June 2012 · case 13/KPPU-L/2011 · PELELANGAN PAKET PEKERJAAN PEMBANGUNAN JALAN SP. MUTIARA-PESISIR SELATAN DI LINGKUNGAN DINAS PEKERJAAN UMUM KABUPATEN KARIMUN PROVINSI KEPULAUAN RIAU TAHUN ANGGARAN 2011 · fine IDR 100,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 June 2012 · case 13/KPPU-L/2011 · PELELANGAN PAKET PEKERJAAN PEMBANGUNAN JALAN SP. MUTIARA-PESISIR SELATAN DI LINGKUNGAN DINAS PEKERJAAN UMUM KABUPATEN KARIMUN PROVINSI KEPULAUAN RIAU TAHUN ANGGARAN 2011 · fine IDR 75,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 29 June 2012 · case 13/KPPU-L/2011 · PELELANGAN PAKET PEKERJAAN PEMBANGUNAN JALAN SP. MUTIARA-PESISIR SELATAN DI LINGKUNGAN DINAS PEKERJAAN UMUM KABUPATEN KARIMUN PROVINSI KEPULAUAN RIAU TAHUN ANGGARAN 2011 · fine IDR 100,000,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 March 2012 · case 10/KPPU-L/2011 · TENDER PEKERJAAN PENINGKATAN JALAN DI DINAS PEKERJAAN UMUM PERTAMBANGAN DAN ENERGI, KABUPATEN LOMBOK UTARA PROPINSI NUSA TENGGARA BARAT TAHUN ANGGARAN 2010 · fine IDR 200,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 March 2012 · case 10/KPPU-L/2011 · TENDER PEKERJAAN PENINGKATAN JALAN DI DINAS PEKERJAAN UMUM PERTAMBANGAN DAN ENERGI, KABUPATEN LOMBOK UTARA PROPINSI NUSA TENGGARA BARAT TAHUN ANGGARAN 2010 · fine IDR 200,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 March 2012 · case 10/KPPU-L/2011 · TENDER PEKERJAAN PENINGKATAN JALAN DI DINAS PEKERJAAN UMUM PERTAMBANGAN DAN ENERGI, KABUPATEN LOMBOK UTARA PROPINSI NUSA TENGGARA BARAT TAHUN ANGGARAN 2010 · fine IDR 350,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 1 March 2012 · case 10/KPPU-L/2011 · TENDER PEKERJAAN PENINGKATAN JALAN DI DINAS PEKERJAAN UMUM PERTAMBANGAN DAN ENERGI, KABUPATEN LOMBOK UTARA PROPINSI NUSA TENGGARA BARAT TAHUN ANGGARAN 2010 · fine IDR 100,000,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 February 2012 · case 11/KPPU-L/2011 · LELANG JASA PELAYANAN TEKNIK POLA 3 TAHUN 2011-2012 ZONA I (UPJ JEMBER KOTA, UPJ KALISAT, UPJ AMBULU) ZONA II (UPJ TANGGUL, UPJ KENCONG, UPJ RAMBIPUJI), ZONA III (UPJ LUMAJANG, UPJ KLAKAH, UPJ TEMPEH) DI PT.PLN (PERSERO) APJ JEMBER TAHUN ANGGARAN 2010 · fine IDR 50,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 February 2012 · case 11/KPPU-L/2011 · LELANG JASA PELAYANAN TEKNIK POLA 3 TAHUN 2011-2012 ZONA I (UPJ JEMBER KOTA, UPJ KALISAT, UPJ AMBULU) ZONA II (UPJ TANGGUL, UPJ KENCONG, UPJ RAMBIPUJI), ZONA III (UPJ LUMAJANG, UPJ KLAKAH, UPJ TEMPEH) DI PT.PLN (PERSERO) APJ JEMBER TAHUN ANGGARAN 2010 · fine IDR 571,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 February 2012 · case 11/KPPU-L/2011 · LELANG JASA PELAYANAN TEKNIK POLA 3 TAHUN 2011-2012 ZONA I (UPJ JEMBER KOTA, UPJ KALISAT, UPJ AMBULU) ZONA II (UPJ TANGGUL, UPJ KENCONG, UPJ RAMBIPUJI), ZONA III (UPJ LUMAJANG, UPJ KLAKAH, UPJ TEMPEH) DI PT.PLN (PERSERO) APJ JEMBER TAHUN ANGGARAN 2010 · fine IDR 115,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 February 2012 · case 11/KPPU-L/2011 · LELANG JASA PELAYANAN TEKNIK POLA 3 TAHUN 2011-2012 ZONA I (UPJ JEMBER KOTA, UPJ KALISAT, UPJ AMBULU) ZONA II (UPJ TANGGUL, UPJ KENCONG, UPJ RAMBIPUJI), ZONA III (UPJ LUMAJANG, UPJ KLAKAH, UPJ TEMPEH) DI PT.PLN (PERSERO) APJ JEMBER TAHUN ANGGARAN 2010 · fine IDR 115,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 January 2012 · case 09/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA DI DINAS PERHUBUNGAN KABUPATEN KUTAI KERTANEGARA PROVINSI KALIMANTAN TIMUR TAHUN ANGGARAN 2009 · fine IDR 579,150,000 · barred from tenders for 3 years · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 January 2012 · case 09/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA DI DINAS PERHUBUNGAN KABUPATEN KUTAI KERTANEGARA PROVINSI KALIMANTAN TIMUR TAHUN ANGGARAN 2009 · fine IDR 473,850,000 · barred from tenders for 1 year · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 January 2012 · case 09/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA DI DINAS PERHUBUNGAN KABUPATEN KUTAI KERTANEGARA PROVINSI KALIMANTAN TIMUR TAHUN ANGGARAN 2009 · fine IDR 579,150,000 · barred from tenders for 2 years · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Penata Karya Keluarga Utama
Authority Indonesia Competition Commission (KPPU) · From 17 January 2012 · case 09/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA DI DINAS PERHUBUNGAN KABUPATEN KUTAI KERTANEGARA PROVINSI KALIMANTAN TIMUR TAHUN ANGGARAN 2009 · fine IDR 473,850,000 · barred from tenders for 1 year · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Kharisma Tropisindo Makmur Abadi
Authority Indonesia Competition Commission (KPPU) · From 17 January 2012 · case 09/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA DI DINAS PERHUBUNGAN KABUPATEN KUTAI KERTANEGARA PROVINSI KALIMANTAN TIMUR TAHUN ANGGARAN 2009 · fine IDR 579,150,000 · barred from tenders for 2 years · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 27 December 2011 · case 07/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA, PEMBANGUNAN PELABUHAN TERPADU DI KECAMATAN KOTA BANGUN PADA PAKET PEMBANGUNAN PELABUHAN TERPADU KECAMATAN KOTA BANGUN DI DINAS PERHUBUNGAN KABUPATEN KUTAI KERTANEGARA PROVINSI KALIMANTAN TIMUR TAHUN ANGGARAN 2009 · fine IDR 735,264,000 · barred from tenders for 1 year · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 27 December 2011 · case 07/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA, PEMBANGUNAN PELABUHAN TERPADU DI KECAMATAN KOTA BANGUN PADA PAKET PEMBANGUNAN PELABUHAN TERPADU KECAMATAN KOTA BANGUN DI DINAS PERHUBUNGAN KABUPATEN KUTAI KERTANEGARA PROVINSI KALIMANTAN TIMUR TAHUN ANGGARAN 2009 · fine IDR 703,296,000,000 · barred from tenders for 2 years · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 27 December 2011 · case 07/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA, PEMBANGUNAN PELABUHAN TERPADU DI KECAMATAN KOTA BANGUN PADA PAKET PEMBANGUNAN PELABUHAN TERPADU KECAMATAN KOTA BANGUN DI DINAS PERHUBUNGAN KABUPATEN KUTAI KERTANEGARA PROVINSI KALIMANTAN TIMUR TAHUN ANGGARAN 2009 · fine IDR 703,296,000,000 · barred from tenders for 2 years · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 27 December 2011 · case 07/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA, PEMBANGUNAN PELABUHAN TERPADU DI KECAMATAN KOTA BANGUN PADA PAKET PEMBANGUNAN PELABUHAN TERPADU KECAMATAN KOTA BANGUN DI DINAS PERHUBUNGAN KABUPATEN KUTAI KERTANEGARA PROVINSI KALIMANTAN TIMUR TAHUN ANGGARAN 2009 · barred from tenders for 1 year · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 27 December 2011 · case 07/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA, PEMBANGUNAN PELABUHAN TERPADU DI KECAMATAN KOTA BANGUN PADA PAKET PEMBANGUNAN PELABUHAN TERPADU KECAMATAN KOTA BANGUN DI DINAS PERHUBUNGAN KABUPATEN KUTAI KERTANEGARA PROVINSI KALIMANTAN TIMUR TAHUN ANGGARAN 2009 · fine IDR 703,296,000,000 · barred from tenders for 2 years · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 November 2011 · case 08/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA, PEMBANGUNAN PELABUHAN TERPADU DI KECAMATAN KOTA BANGUN PADA PAKET PEKERJAAN PENDAMPING KEGIATAN PEMBANGUNAN PELABUHAN TERPADU DINAS PERHUBUNGAN KABUPATEN KUTAI KARTANEGARA PROVINSI KALIMANTAN TIMUR · fine IDR 15,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 November 2011 · case 08/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA, PEMBANGUNAN PELABUHAN TERPADU DI KECAMATAN KOTA BANGUN PADA PAKET PEKERJAAN PENDAMPING KEGIATAN PEMBANGUNAN PELABUHAN TERPADU DINAS PERHUBUNGAN KABUPATEN KUTAI KARTANEGARA PROVINSI KALIMANTAN TIMUR · fine IDR 15,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 November 2011 · case 08/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA, PEMBANGUNAN PELABUHAN TERPADU DI KECAMATAN KOTA BANGUN PADA PAKET PEKERJAAN PENDAMPING KEGIATAN PEMBANGUNAN PELABUHAN TERPADU DINAS PERHUBUNGAN KABUPATEN KUTAI KARTANEGARA PROVINSI KALIMANTAN TIMUR · fine IDR 15,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 18 November 2011 · case 08/KPPU-I/2011 · TENDER PEKERJAAN PEMBANGUNAN PELABUHAN LAUT SAMBOJA, PEMBANGUNAN PELABUHAN TERPADU DI KECAMATAN KOTA BANGUN PADA PAKET PEKERJAAN PENDAMPING KEGIATAN PEMBANGUNAN PELABUHAN TERPADU DINAS PERHUBUNGAN KABUPATEN KUTAI KARTANEGARA PROVINSI KALIMANTAN TIMUR · fine IDR 15,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT. Citra Bangun Adigraha dan PT. Bima Putra Bangsa
Authority Indonesia Competition Commission (KPPU) · From 19 October 2011 · case 03/KPPU-L/2011 · TENDER PEKERJAAN PEMBANGUNAN DAN PENINGKATAN JARINGAN IRIGASI JANGKANG KOMPLEK DI DINAS PEKERJAAN UMUM KABUPATEN SANGGAU, PROPINSI KALIMANTAN BARAT · fine IDR 651,000,000 · barred from tenders for 2 years · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 19 October 2011 · case 03/KPPU-L/2011 · TENDER PEKERJAAN PEMBANGUNAN DAN PENINGKATAN JARINGAN IRIGASI JANGKANG KOMPLEK DI DINAS PEKERJAAN UMUM KABUPATEN SANGGAU, PROPINSI KALIMANTAN BARAT · barred from tenders for 2 years · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 19 October 2011 · case 03/KPPU-L/2011 · TENDER PEKERJAAN PEMBANGUNAN DAN PENINGKATAN JARINGAN IRIGASI JANGKANG KOMPLEK DI DINAS PEKERJAAN UMUM KABUPATEN SANGGAU, PROPINSI KALIMANTAN BARAT · barred from tenders for 2 years · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 19 October 2011 · case 03/KPPU-L/2011 · TENDER PEKERJAAN PEMBANGUNAN DAN PENINGKATAN JARINGAN IRIGASI JANGKANG KOMPLEK DI DINAS PEKERJAAN UMUM KABUPATEN SANGGAU, PROPINSI KALIMANTAN BARAT · barred from tenders for 2 years · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 August 2011 · case 02/KPPU-L/2011 · PELELANGAN PROYEK PEMBANGUNAN JALAN TENGGARONG – SAMBOJA, PERBATASAN DENGAN BALIKPAPAN · fine IDR 100,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 August 2011 · case 02/KPPU-L/2011 · PELELANGAN PROYEK PEMBANGUNAN JALAN TENGGARONG – SAMBOJA, PERBATASAN DENGAN BALIKPAPAN · fine IDR 100,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 August 2011 · case 02/KPPU-L/2011 · PELELANGAN PROYEK PEMBANGUNAN JALAN TENGGARONG – SAMBOJA, PERBATASAN DENGAN BALIKPAPAN · fine IDR 100,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 May 2011 · case 41/KPPU-L/2010 · TENDER PENGADAAN SARANA DAN PRASARANA KONVERSI ENERGI DI LINGKUNGAN DIREKTORAT JENDERAL MINYAK DAN GAS BUMI DEPARTEMEN ENERGI DAN SUMBER DAYA MINERAL TAHUN ANGGARAN 2009 · fine IDR 1 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 May 2011 · case 41/KPPU-L/2010 · TENDER PENGADAAN SARANA DAN PRASARANA KONVERSI ENERGI DI LINGKUNGAN DIREKTORAT JENDERAL MINYAK DAN GAS BUMI DEPARTEMEN ENERGI DAN SUMBER DAYA MINERAL TAHUN ANGGARAN 2009 · fine IDR 655 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 May 2011 · case 41/KPPU-L/2010 · TENDER PENGADAAN SARANA DAN PRASARANA KONVERSI ENERGI DI LINGKUNGAN DIREKTORAT JENDERAL MINYAK DAN GAS BUMI DEPARTEMEN ENERGI DAN SUMBER DAYA MINERAL TAHUN ANGGARAN 2009 · fine IDR 451 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 May 2011 · case 41/KPPU-L/2010 · TENDER PENGADAAN SARANA DAN PRASARANA KONVERSI ENERGI DI LINGKUNGAN DIREKTORAT JENDERAL MINYAK DAN GAS BUMI DEPARTEMEN ENERGI DAN SUMBER DAYA MINERAL TAHUN ANGGARAN 2009 · fine IDR 381 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 May 2011 · case 41/KPPU-L/2010 · TENDER PENGADAAN SARANA DAN PRASARANA KONVERSI ENERGI DI LINGKUNGAN DIREKTORAT JENDERAL MINYAK DAN GAS BUMI DEPARTEMEN ENERGI DAN SUMBER DAYA MINERAL TAHUN ANGGARAN 2009 · fine IDR 335 · respondent IX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Konsorsium PT. Surveyor Indonesia dengan PT. Sucofindo
Authority Indonesia Competition Commission (KPPU) · From 13 May 2011 · case 41/KPPU-L/2010 · TENDER PENGADAAN SARANA DAN PRASARANA KONVERSI ENERGI DI LINGKUNGAN DIREKTORAT JENDERAL MINYAK DAN GAS BUMI DEPARTEMEN ENERGI DAN SUMBER DAYA MINERAL TAHUN ANGGARAN 2009 · fine IDR 220 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 May 2011 · case 41/KPPU-L/2010 · TENDER PENGADAAN SARANA DAN PRASARANA KONVERSI ENERGI DI LINGKUNGAN DIREKTORAT JENDERAL MINYAK DAN GAS BUMI DEPARTEMEN ENERGI DAN SUMBER DAYA MINERAL TAHUN ANGGARAN 2009 · fine IDR 667 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT. Kencana Mandiri Uli Nusantara
Authority Indonesia Competition Commission (KPPU) · From 13 May 2011 · case 41/KPPU-L/2010 · TENDER PENGADAAN SARANA DAN PRASARANA KONVERSI ENERGI DI LINGKUNGAN DIREKTORAT JENDERAL MINYAK DAN GAS BUMI DEPARTEMEN ENERGI DAN SUMBER DAYA MINERAL TAHUN ANGGARAN 2009 · fine IDR 267 · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 13 May 2011 · case 41/KPPU-L/2010 · TENDER PENGADAAN SARANA DAN PRASARANA KONVERSI ENERGI DI LINGKUNGAN DIREKTORAT JENDERAL MINYAK DAN GAS BUMI DEPARTEMEN ENERGI DAN SUMBER DAYA MINERAL TAHUN ANGGARAN 2009 · fine IDR 312 · respondent X of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 March 2011 · case 40/KPPU-L/2010 · PELELANGAN PEKERJAAN PENGADAAN DAN PEMASANGAN MARKA DI DINAS PERHUBUNGAN PROVINSI JAWA BARAT · fine IDR 25,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Lintasmarga Nusantara Djaya
Authority Indonesia Competition Commission (KPPU) · From 30 March 2011 · case 40/KPPU-L/2010 · PELELANGAN PEKERJAAN PENGADAAN DAN PEMASANGAN MARKA DI DINAS PERHUBUNGAN PROVINSI JAWA BARAT · fine IDR 10,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 4 March 2011 · case 38/KPPU-L/2010 · LELANG CONTRACT PACKAGE NO. 3A BOJONEGARA – CIKANDE DISTRIBUTION PIPELINE · fine IDR 6,000,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Perusahaan Gas Negara (Persero) Tbk
Authority Indonesia Competition Commission (KPPU) · From 4 March 2011 · case 38/KPPU-L/2010 · LELANG CONTRACT PACKAGE NO. 3A BOJONEGARA – CIKANDE DISTRIBUTION PIPELINE · fine IDR 6,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 9 December 2010 · case 31/KPPU-L/2010 · TENDER NO. SPM-002 INTEGRATED DRILLING SERVICES FOR EXPLORATION WELLS IN MADURA ISLAND BLOCK · fine IDR 2,500,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 9 December 2010 · case 31/KPPU-L/2010 · TENDER NO. SPM-002 INTEGRATED DRILLING SERVICES FOR EXPLORATION WELLS IN MADURA ISLAND BLOCK · fine IDR 2,500,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 November 2010 · case 29/KPPU-L/2010 · PENGADAAN PESTISIDA UNTUK PEREMAJAAN, REHABILITASI, DAN INTENSIFIKASI KEGIATAN GERAKAN PENINGKATAN PRODUKSI DAN MUTU KAKAO NASIONAL TAHUN 2009 SATKER DINAS PERKEBUNAN DAN HOLTIKULTURA PROVINSI SULAWESI TENGGARA · fine IDR 1,500,000,000 · barred from tenders for 1 year (Indonesia) · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 November 2010 · case 29/KPPU-L/2010 · PENGADAAN PESTISIDA UNTUK PEREMAJAAN, REHABILITASI, DAN INTENSIFIKASI KEGIATAN GERAKAN PENINGKATAN PRODUKSI DAN MUTU KAKAO NASIONAL TAHUN 2009 SATKER DINAS PERKEBUNAN DAN HOLTIKULTURA PROVINSI SULAWESI TENGGARA · fine IDR 500,000,000 · barred from tenders for 1 year (Indonesia) · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 November 2010 · case 29/KPPU-L/2010 · PENGADAAN PESTISIDA UNTUK PEREMAJAAN, REHABILITASI, DAN INTENSIFIKASI KEGIATAN GERAKAN PENINGKATAN PRODUKSI DAN MUTU KAKAO NASIONAL TAHUN 2009 SATKER DINAS PERKEBUNAN DAN HOLTIKULTURA PROVINSI SULAWESI TENGGARA · fine IDR 500,000,000 · barred from tenders for 1 year (Indonesia) · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 November 2010 · case 29/KPPU-L/2010 · PENGADAAN PESTISIDA UNTUK PEREMAJAAN, REHABILITASI, DAN INTENSIFIKASI KEGIATAN GERAKAN PENINGKATAN PRODUKSI DAN MUTU KAKAO NASIONAL TAHUN 2009 SATKER DINAS PERKEBUNAN DAN HOLTIKULTURA PROVINSI SULAWESI TENGGARA · fine IDR 500,000,000 · barred from tenders for 1 year (Indonesia) · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 November 2010 · case 30/KPPU-L/2010 · TENDER 6 (ENAM) PAKET PEKERJAAN DI LINGKUNGAN UNIT PENGADAAN BARANG DAN JASA (UPBJ) PEMERINTAH KABUPATEN LINGGA TAHUN ANGGARAN 2009 · fine IDR 151,100,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 November 2010 · case 30/KPPU-L/2010 · TENDER 6 (ENAM) PAKET PEKERJAAN DI LINGKUNGAN UNIT PENGADAAN BARANG DAN JASA (UPBJ) PEMERINTAH KABUPATEN LINGGA TAHUN ANGGARAN 2009 · fine IDR 95,090,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 November 2010 · case 30/KPPU-L/2010 · TENDER 6 (ENAM) PAKET PEKERJAAN DI LINGKUNGAN UNIT PENGADAAN BARANG DAN JASA (UPBJ) PEMERINTAH KABUPATEN LINGGA TAHUN ANGGARAN 2009 · fine IDR 99,200,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 November 2010 · case 30/KPPU-L/2010 · TENDER 6 (ENAM) PAKET PEKERJAAN DI LINGKUNGAN UNIT PENGADAAN BARANG DAN JASA (UPBJ) PEMERINTAH KABUPATEN LINGGA TAHUN ANGGARAN 2009 · fine IDR 97,100,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 November 2010 · case 30/KPPU-L/2010 · TENDER 6 (ENAM) PAKET PEKERJAAN DI LINGKUNGAN UNIT PENGADAAN BARANG DAN JASA (UPBJ) PEMERINTAH KABUPATEN LINGGA TAHUN ANGGARAN 2009 · respondent IX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 November 2010 · case 30/KPPU-L/2010 · TENDER 6 (ENAM) PAKET PEKERJAAN DI LINGKUNGAN UNIT PENGADAAN BARANG DAN JASA (UPBJ) PEMERINTAH KABUPATEN LINGGA TAHUN ANGGARAN 2009 · fine IDR 63,100,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 November 2010 · case 30/KPPU-L/2010 · TENDER 6 (ENAM) PAKET PEKERJAAN DI LINGKUNGAN UNIT PENGADAAN BARANG DAN JASA (UPBJ) PEMERINTAH KABUPATEN LINGGA TAHUN ANGGARAN 2009 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 November 2010 · case 30/KPPU-L/2010 · TENDER 6 (ENAM) PAKET PEKERJAAN DI LINGKUNGAN UNIT PENGADAAN BARANG DAN JASA (UPBJ) PEMERINTAH KABUPATEN LINGGA TAHUN ANGGARAN 2009 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 November 2010 · case 30/KPPU-L/2010 · TENDER 6 (ENAM) PAKET PEKERJAAN DI LINGKUNGAN UNIT PENGADAAN BARANG DAN JASA (UPBJ) PEMERINTAH KABUPATEN LINGGA TAHUN ANGGARAN 2009 · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 November 2010 · case 30/KPPU-L/2010 · TENDER 6 (ENAM) PAKET PEKERJAAN DI LINGKUNGAN UNIT PENGADAAN BARANG DAN JASA (UPBJ) PEMERINTAH KABUPATEN LINGGA TAHUN ANGGARAN 2009 · respondent X of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · fine IDR 59,743,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · fine IDR 226,782,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · fine IDR 659,123,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · fine IDR 599,499,000 · respondent IX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · fine IDR 187,275,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · fine IDR 52,428,000 · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · respondent X of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · respondent XI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · respondent XII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · respondent XIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · respondent XIV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · fine IDR 449,844,000 · respondent XV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · respondent XVI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · respondent XVII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · respondent XVIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 15 November 2010 · case 26/KPPU-L/2010 · LELANG PEKERJAAN DI DINAS PEKERJAAN UMUM BINA MARGA KABUPATEN OGAN KOMERING ULU PROVINSI SUMATERA SELATAN · respondent XX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Asria Nurlindra Inti Sejahtera
Authority Indonesia Competition Commission (KPPU) · From 5 November 2010 · case 33/KPPU-L/2010 · TENDER PAKET PEKERJAAN DI DINAS BINA MARGA, SUMBER DAYA AIR DAN ESDM KOTA SINGKAWANG · fine IDR 40,000,000 · barred from tenders for 1 year (Kabupaten Singkawang) · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 November 2010 · case 33/KPPU-L/2010 · TENDER PAKET PEKERJAAN DI DINAS BINA MARGA, SUMBER DAYA AIR DAN ESDM KOTA SINGKAWANG · barred from tenders for 1 year (Kabupaten Singkawang) · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 November 2010 · case 33/KPPU-L/2010 · TENDER PAKET PEKERJAAN DI DINAS BINA MARGA, SUMBER DAYA AIR DAN ESDM KOTA SINGKAWANG · fine IDR 100,000,000 · barred from tenders for 1 year (Kabupaten Singkawang) · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 November 2010 · case 33/KPPU-L/2010 · TENDER PAKET PEKERJAAN DI DINAS BINA MARGA, SUMBER DAYA AIR DAN ESDM KOTA SINGKAWANG · barred from tenders for 1 year (Kabupaten Singkawang) · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 November 2010 · case 33/KPPU-L/2010 · TENDER PAKET PEKERJAAN DI DINAS BINA MARGA, SUMBER DAYA AIR DAN ESDM KOTA SINGKAWANG · fine IDR 55,000,000 · barred from tenders for 1 year (Kabupaten Singkawang) · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 5 November 2010 · case 33/KPPU-L/2010 · TENDER PAKET PEKERJAAN DI DINAS BINA MARGA, SUMBER DAYA AIR DAN ESDM KOTA SINGKAWANG · fine IDR 50,000,000 · barred from tenders for 1 year (Kabupaten Singkawang) · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 November 2010 · case 25/KPPU-L/2010 · PENGADAAN BARANG/JASA PEMERINTAH DI LINGKUNGAN DINAS PEKERJAAN UMUM PROVINSI RIAU · fine IDR 200,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 November 2010 · case 25/KPPU-L/2010 · PENGADAAN BARANG/JASA PEMERINTAH DI LINGKUNGAN DINAS PEKERJAAN UMUM PROVINSI RIAU · fine IDR 100,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 November 2010 · case 25/KPPU-L/2010 · PENGADAAN BARANG/JASA PEMERINTAH DI LINGKUNGAN DINAS PEKERJAAN UMUM PROVINSI RIAU · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 November 2010 · case 25/KPPU-L/2010 · PENGADAAN BARANG/JASA PEMERINTAH DI LINGKUNGAN DINAS PEKERJAAN UMUM PROVINSI RIAU · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 November 2010 · case 25/KPPU-L/2010 · PENGADAAN BARANG/JASA PEMERINTAH DI LINGKUNGAN DINAS PEKERJAAN UMUM PROVINSI RIAU · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 November 2010 · case 25/KPPU-L/2010 · PENGADAAN BARANG/JASA PEMERINTAH DI LINGKUNGAN DINAS PEKERJAAN UMUM PROVINSI RIAU · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 3 November 2010 · case 25/KPPU-L/2010 · PENGADAAN BARANG/JASA PEMERINTAH DI LINGKUNGAN DINAS PEKERJAAN UMUM PROVINSI RIAU · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 19 October 2010 · case 22/KPPU-L/2010 · TENDER PAKET PEKERJAAN REKLAMASI PERLUASAN OPEN STORAGE PELABUHAN CPO KABIL · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 19 October 2010 · case 22/KPPU-L/2010 · TENDER PAKET PEKERJAAN REKLAMASI PERLUASAN OPEN STORAGE PELABUHAN CPO KABIL · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · fine IDR 100,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · barred from tenders for 1 year · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Bumi Melayu Indah Sejahtera
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · fine IDR 150,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · barred from tenders for 1 year · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · barred from tenders for 1 year · respondent IX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · fine IDR 100,000,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · barred from tenders for 1 year · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · fine IDR 300,000,000 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · fine IDR 300,000,000 · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · barred from tenders for 1 year · respondent X of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · fine IDR 150,000,000 · respondent XI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · fine IDR 75,000,000 · respondent XII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · fine IDR 100,000,000 · respondent XIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · barred from tenders for 1 year · respondent XIV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · barred from tenders for 1 year · respondent XIX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · fine IDR 125,000,000 · respondent XV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · barred from tenders for 1 year · respondent XVI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · barred from tenders for 2 years · respondent XVII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · barred from tenders for 2 years · respondent XVIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · barred from tenders for 1 year · respondent XX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · fine IDR 150,000,000 · respondent XXI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 19/KPPU-L/2010 · TENDER KONSTRUKSI BIDANG JALAN DAN JEMBATAN KABUPATEN BENGKALIS · barred from tenders for 2 years · respondent XXII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 20/KPPU-L/2010 · TENDER KEGIATAN KEBERSIHAN KANTOR SEKRETARIAT DAERAH PROVINSI RIAU · fine IDR 179,216,400 · barred from tenders for 2 years · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 20/KPPU-L/2010 · TENDER KEGIATAN KEBERSIHAN KANTOR SEKRETARIAT DAERAH PROVINSI RIAU · barred from tenders for 2 years · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 20/KPPU-L/2010 · TENDER KEGIATAN KEBERSIHAN KANTOR SEKRETARIAT DAERAH PROVINSI RIAU · fine IDR 427,588,500 · barred from tenders for 2 years · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 October 2010 · case 20/KPPU-L/2010 · TENDER KEGIATAN KEBERSIHAN KANTOR SEKRETARIAT DAERAH PROVINSI RIAU · barred from tenders for 2 years · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2010 · case 14/KPPU-L/2010 · PENGADAAN BARANG DAN JASA PEMBORONGAN DAN JASA KONSULTAN PADA DINAS PEKERJAAN UMUM KABUPATEN TEBO, JAMBI · fine IDR 1,240,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2010 · case 14/KPPU-L/2010 · PENGADAAN BARANG DAN JASA PEMBORONGAN DAN JASA KONSULTAN PADA DINAS PEKERJAAN UMUM KABUPATEN TEBO, JAMBI · fine IDR 800,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2010 · case 14/KPPU-L/2010 · PENGADAAN BARANG DAN JASA PEMBORONGAN DAN JASA KONSULTAN PADA DINAS PEKERJAAN UMUM KABUPATEN TEBO, JAMBI · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2010 · case 14/KPPU-L/2010 · PENGADAAN BARANG DAN JASA PEMBORONGAN DAN JASA KONSULTAN PADA DINAS PEKERJAAN UMUM KABUPATEN TEBO, JAMBI · respondent IX of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2010 · case 14/KPPU-L/2010 · PENGADAAN BARANG DAN JASA PEMBORONGAN DAN JASA KONSULTAN PADA DINAS PEKERJAAN UMUM KABUPATEN TEBO, JAMBI · fine IDR 160,000,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2010 · case 14/KPPU-L/2010 · PENGADAAN BARANG DAN JASA PEMBORONGAN DAN JASA KONSULTAN PADA DINAS PEKERJAAN UMUM KABUPATEN TEBO, JAMBI · fine IDR 145,000,000 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2010 · case 14/KPPU-L/2010 · PENGADAAN BARANG DAN JASA PEMBORONGAN DAN JASA KONSULTAN PADA DINAS PEKERJAAN UMUM KABUPATEN TEBO, JAMBI · fine IDR 85,000,000 · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2010 · case 14/KPPU-L/2010 · PENGADAAN BARANG DAN JASA PEMBORONGAN DAN JASA KONSULTAN PADA DINAS PEKERJAAN UMUM KABUPATEN TEBO, JAMBI · respondent VIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2010 · case 14/KPPU-L/2010 · PENGADAAN BARANG DAN JASA PEMBORONGAN DAN JASA KONSULTAN PADA DINAS PEKERJAAN UMUM KABUPATEN TEBO, JAMBI · respondent X of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2010 · case 14/KPPU-L/2010 · PENGADAAN BARANG DAN JASA PEMBORONGAN DAN JASA KONSULTAN PADA DINAS PEKERJAAN UMUM KABUPATEN TEBO, JAMBI · fine IDR 275,000,000 · respondent XI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2010 · case 14/KPPU-L/2010 · PENGADAAN BARANG DAN JASA PEMBORONGAN DAN JASA KONSULTAN PADA DINAS PEKERJAAN UMUM KABUPATEN TEBO, JAMBI · respondent XII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 23 September 2010 · case 14/KPPU-L/2010 · PENGADAAN BARANG DAN JASA PEMBORONGAN DAN JASA KONSULTAN PADA DINAS PEKERJAAN UMUM KABUPATEN TEBO, JAMBI · respondent XIII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 September 2010 · case 18/KPPU-L/2010 · LELANG KONSTRUKSI PEMBANGUNAN GEDUNG ASRAMA MAHASISWA MA – HAD ALY UIN ALAUDDIN MAKASSAR · fine IDR 100,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 September 2010 · case 18/KPPU-L/2010 · LELANG KONSTRUKSI PEMBANGUNAN GEDUNG ASRAMA MAHASISWA MA – HAD ALY UIN ALAUDDIN MAKASSAR · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 22 September 2010 · case 18/KPPU-L/2010 · LELANG KONSTRUKSI PEMBANGUNAN GEDUNG ASRAMA MAHASISWA MA – HAD ALY UIN ALAUDDIN MAKASSAR · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 September 2010 · case 09/KPPU-L/2010 · PAKET PEKERJAAN TANGGUL PENGAMAN TERMASUK JALAN INSPEKSI (TPJIP) TELUK TAHUNA KABUPATEN KEPULAUAN SANGIHE · fine IDR 400,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 September 2010 · case 09/KPPU-L/2010 · PAKET PEKERJAAN TANGGUL PENGAMAN TERMASUK JALAN INSPEKSI (TPJIP) TELUK TAHUNA KABUPATEN KEPULAUAN SANGIHE · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 September 2010 · case 09/KPPU-L/2010 · PAKET PEKERJAAN TANGGUL PENGAMAN TERMASUK JALAN INSPEKSI (TPJIP) TELUK TAHUNA KABUPATEN KEPULAUAN SANGIHE · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 September 2010 · case 09/KPPU-L/2010 · PAKET PEKERJAAN TANGGUL PENGAMAN TERMASUK JALAN INSPEKSI (TPJIP) TELUK TAHUNA KABUPATEN KEPULAUAN SANGIHE · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 20 September 2010 · case 09/KPPU-L/2010 · PAKET PEKERJAAN TANGGUL PENGAMAN TERMASUK JALAN INSPEKSI (TPJIP) TELUK TAHUNA KABUPATEN KEPULAUAN SANGIHE · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 September 2010 · case 11/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · fine IDR 750,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 September 2010 · case 11/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 September 2010 · case 11/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 September 2010 · case 11/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 September 2010 · case 11/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 17 September 2010 · case 11/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · respondent VII of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Karya Bunga Pantai Ceria Group
Authority Indonesia Competition Commission (KPPU) · From 6 September 2010 · case 08/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 September 2010 · case 08/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 September 2010 · case 08/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 6 September 2010 · case 08/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 31 August 2010 · case 05/KPPU-L/2010 · PENGADAAN 20 (DUA PULUH) UNIT LOKOMOTIF CC 204 TAHUN 2009 · fine IDR 2,000,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT Pembangunan Perumahan (Persero)
Authority Indonesia Competition Commission (KPPU) · From 19 August 2010 · case 02/KPPU-L/2010 · TENDER PEMBANGUNAN RUMAH SAKIT PENDIDIKAN (TEACHING HOSPITAL) TAHAP II UNIVERSITAS HASANUDDIN MAKASSAR · fine IDR 5,000,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 July 2010 · case 10/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · fine IDR 100,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 July 2010 · case 10/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · fine IDR 100,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 30 July 2010 · case 10/KPPU-L/2010 · LELANG PRAKONSTRUKSI BANDAR UDARA MUARA BUNGO JAMBI · fine IDR 100,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 27 July 2010 · case 03/KPPU-L/2010 · TENDER PENGEMBANGAN DAN PENGELOLAAN JARINGAN IRIGASI, RAWA, DAN JARINGAN PENGAIRAN LAINNYA KABUPATEN PANGKAJENE · barred from tenders for 1 year · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
CV Global Inc., pada saat tender
Authority Indonesia Competition Commission (KPPU) · From 27 July 2010 · case 07/KPPU-L/2010 · LELANG PENGADAAN ALAT-ALAT LABORATORIUM BAHASA DINAS PENDIDIKAN, PEMUDA, DAN OLAHRAGA KABUPATEN KUDUS TAHUN ANGGARAN 2009 · fine IDR 147,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 27 July 2010 · case 07/KPPU-L/2010 · LELANG PENGADAAN ALAT-ALAT LABORATORIUM BAHASA DINAS PENDIDIKAN, PEMUDA, DAN OLAHRAGA KABUPATEN KUDUS TAHUN ANGGARAN 2009 · fine IDR 54,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT. Bunga Raya Lestari Jo PT. Citra Nusra Persada
Authority Indonesia Competition Commission (KPPU) · From 16 June 2010 · case 34/KPPU-L/2009 · TENDER PENANGANAN JALAN DAN JEMBATAN KABUPATEN BIMA · fine IDR 1,950,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 16 June 2010 · case 34/KPPU-L/2009 · TENDER PENANGANAN JALAN DAN JEMBATAN KABUPATEN BIMA · fine IDR 975,000,000 · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 16 June 2010 · case 34/KPPU-L/2009 · TENDER PENANGANAN JALAN DAN JEMBATAN KABUPATEN BIMA · fine IDR 975,000,000 · respondent III of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 16 June 2010 · case 34/KPPU-L/2009 · TENDER PENANGANAN JALAN DAN JEMBATAN KABUPATEN BIMA · fine IDR 150,000,000 · respondent IV of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 16 June 2010 · case 34/KPPU-L/2009 · TENDER PENANGANAN JALAN DAN JEMBATAN KABUPATEN BIMA · fine IDR 75,000,000 · respondent V of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
Authority Indonesia Competition Commission (KPPU) · From 16 June 2010 · case 34/KPPU-L/2009 · TENDER PENANGANAN JALAN DAN JEMBATAN KABUPATEN BIMA · fine IDR 75,000,000 · respondent VI of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT. Taramulia Setia Pratama Luhur, pelaku usaha
Authority Indonesia Competition Commission (KPPU) · From 1 June 2010 · case 30/KPPU-I/2009 · LELANG BANGUNAN SEKOLAH DAN KESEHATAN KABUPATEN NIAS · fine IDR 200,000,000 · respondent I of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT. Untario Metalindo, pelaku usaha
Authority Indonesia Competition Commission (KPPU) · From 1 June 2010 · case 30/KPPU-I/2009 · LELANG BANGUNAN SEKOLAH DAN KESEHATAN KABUPATEN NIAS · respondent II of the case; the ruling may have been appealed in court · Source
Bid rigging in a tender (Article 22, Law 5/1999)
PT. Eka Perkasa Indah, pelaku usaha
Authority Indonesia Competition Commission (KPPU) · From 1 June 2010 · case 30/KPPU-I/2009 · LELANG BANGUNAN SEKOLAH DAN KESEHATAN KABUPATEN NIAS · respondent III of the case; the ruling may have been appealed in court · Source
1 2